NYISO Short-Term Assessment of Reliability July 2023

On July 14, 2023 the New York Independent System Operator (NYISO) released its quarterly assessment of reliability of the bulk electric system.  The analysis found a deficit in reliability margins for the New York City area beginning in summer 2025. As a result, something must be done or there will be unacceptable risks to reliability that could cause power outages.  Unfortunately, it is difficult to understand the reasons for this finding because of the complexity of the subject.  This post includes a detailed explanation of the report and its implications.  If you want a good non-technical summary, then I recommend James Hanley’s post Get Ready for the New York City Blackout of 2025.

I have been following the Climate Leadership & Community Protection Act (Climate Act) since it was first proposed.  I submitted comments on the Climate Act implementation plan and have written over 300 articles about New York’s net-zero transition.  I have devoted a lot of time to the Climate Act and New York’s energy planning because I believe the ambitions for a zero-emissions economy embodied in the Climate Act outstrip available renewable technology such that the net-zero transition will do more harm than good.  Unfortunately, trying to explain the risks and issues associated with the transition is difficult because of the complexity of the problems and the fact that expert reports are dense and filled with jargon.  The opinions expressed in this article do not reflect the position any of my previous employers or any other company I have been associated with, these comments are mine alone.

Resource Adequacy Assessments

The NYISO is responsible power system reliability and competitive markets for New York.  As part of that mission NYISO determines whether generating resources and the transmission system can adequately meet expected load.  They describe the resource adequacy analyses as follows:

Resource adequacy is the ability of the electric system to supply the aggregate electrical demand and energy requirements of the firm load at all times, considering scheduled and reasonably expected unscheduled outages of system elements. The NYISO performs resource adequacy assessments on a probabilistic basis to capture the random nature of system element outages. If a system has sufficient transmission and generation, the probability of an unplanned disconnection of firm load is equal to or less than the system’s standard, which is expressed as a loss of load expectation (LOLE). Consistent with the Northeast Power Coordinating Council and New York State Reliability Council criterion, the New York State bulk power system is planned to meet an LOLE that, at any given point in time, is less than or equal to an involuntary firm load disconnection that is not more frequent than once in every 10 years, or 0.1 event days per year.

So what does that mean?  The first point is that the electric system is very complicated.  I summarized my skepticism of the net-zero transition earlier this year in an article that included an overview of the electric system.   Incredibly all the fossil, hydro, and nuclear generating stations in the Eastern Interconnection shown below work together.  In order to provide electricity, the generating turbines are synchronized to turn at 1800 revolutions per minute.  Operators keeps the voltages as constant as possible in the entire area but rely on those turbines to provide inertia as well as voltage control and that can be dispatched as necessary to match load.  The NYISO operates the New York State control area within the Interconnection.  In addition to the day-to-day operation, they plan for resource adequacy to ensure that the operators have generating resources available so that they can constantly match load. 

The NYISO resource adequacy assessments rely on decades of observed characteristics of generating resources, the transmission system, and system load to develop the likelihood  of system element outages. If a system has sufficient transmission and generation, then when a problem occurs (say lightning hits a transmission line) the system can respond without an extended outage.  The NYISO has a well-established process to identify reliability needs. The analyses consider how the system can react to various combinations of issues based on historical observations of the existing system to determine the loss of load expectation (LOLE). The organizations overseeing New York reliability,  the Northeast Power Coordinating Council and New York State Reliability Council, mandate that the New York State bulk power system is planned to meet the LOLE standard that any involuntary firm load disconnection  is not more frequent than once in every 10 years, or 0.1 event days per year.

Annotated Executive Summary

This section quotes the Executive Summary in the report and explains the contents.  As part of an on-going reliability assessment process the NYISO analyzes any expected changes to the generation and transmission system:

This report sets forth the 2023 Quarter 2 Short-Term Assessment of Reliability (“STAR”) findings for the five-year study period of April 15, 2023, through April 15, 2028, considering forecasts of peak power demand, planned upgrades to the transmission system, and changes to the generation mix over the next five years.

The analysis finds that there are issues associated with peaking power plants in New York City.  I have been involved with this problem and these facilities since 2000.  This topic has been the subject of multiple articles on this blog and I have summarized my articles as on overview that I can reference when the issue resurfaces.  The Executive Summary notes: 

This assessment finds a reliability need beginning in summer 2025 within New York City primarily driven by a combination of forecasted increases in peak demand and the assumed unavailability of certain generation in New York City affected by the “Peaker Rule.”  In 2019, the New York State Department of Environmental Conservation adopted a regulation to limit nitrogen oxides (NOx) emissions from simple-cycle combustion turbines, referred to as the “Peaker Rule” (https://www.dec.ny.gov/regulations/116131.html)  

The Peaker Rule culminated a decade-long process whereby the New York State Department of Environmental Conservation (DEC) instituted a framework to retire or control the “peakers”.  The DEC, NYISO, facility owners and Consolidate Edison, the load serving entity for New York City, all worked together to ensure that the retirement would not endanger reliability.  This latest analysis suggests that there are still issues to be resolved:

Combustion turbines known as “peakers” typically operate to maintain bulk power system reliability during the most stressful operating conditions, such as periods of peak electricity demand. As of May 1, 2023, 1,027 MW of affected peakers have deactivated or limited their operation. An additional 590 MW of peakers are expected to become unavailable beginning May 1, 2025, all of which are in New York City.   With the additional peakers unavailable, the bulk power transmission system will not be able to securely and reliably serve the forecasted demand in New York City (Zone J). Specifically, the New York City zone is deficient by as much as 446 MW for a duration of nine hours on the peak day during expected weather conditions when accounting for forecasted economic growth and policy-driven increases in demand.

The following paragraph explains that the reliability need is expected because the latest projections of generation, load, and transmission availability have changed over time:

The reliability need is based on a deficient transmission security margin that accounts for expected generator availability, transmission limitations, and updated demand forecasts using data published in the 2023 Load & Capacity Data Report (“Gold Book”). The transmission security margin represents the balance between demand for electricity and the power supply available from generation and transmission to serve that demand. This assessment recognizes that there is uncertainty in the demand forecast due to uncertainties in key assumptions including population and economic growth, the proliferation of energy efficiency, the installation of behind-the-meter renewable energy resources, and electric vehicle adoption and charging patterns. These risks are accounted for in the transmission security margin calculations by incorporating the lower and higher bounds as a range of forecasted conditions during expected weather, specified in the Gold Book as the policy scenario forecasts. The lower and higher demand policy scenario forecasts reflect achievement of policy targets through alternative pathways and assume the same weather factors as the baseline demand forecast.

The Gold Book is the standard for electric data in New York. The following figure shows the range of the demand forecasts for New York City.  I want to point out one thing.  The emphasis is on providing generation for the peak load.  This is a significantly more difficult problem than estimating the generation necessary for an average year.  There are more short-term constraints that could affect generation and load that can be ignored on average.  

I have some experience with the resource modeling projections and cannot over-emphasize the complexity of all the factors incorporated in the models.  Unfortunately, there is a lot of uncertainty associated with projecting all those factors.  That is why the NYISO is constantly re-evaluating the model inputs and projections.  In addition, they are always looking to refine the model itself.  Based on their latest estimates:

Under the baseline forecast for coincident summer peak demand, the New York City transmission security margin would be deficient by 306 MW in 2025 for a duration of 7 hours. However, accounting for uncertainties in key demand forecast assumptions, the higher bound of expected demand under baseline weather conditions (95 degrees Fahrenheit) in 2025 results in a deficiency of 446 MW over 9 hours. The deficiency would be significantly greater if New York City experiences a heatwave (98 degrees Fahrenheit) or an extreme heatwave (102 degrees Fahrenheit).

The NYISO is banking on one project to address this problem after 2025.

Overall, the New York City transmission security margin is expected to improve in 2026 if the Champlain Hudson Power Express (CHPE) connection from Hydro Quebec to New York City enters service on schedule in spring 2026, but the margin gradually erodes through time thereafter as expected demand for electricity grows. Beyond 2025, the forecasted reliability margins within New York City may not be sufficient if (i) the CHPE project experiences a significant delay, (ii) additional power plants become unavailable, or (iii) demand significantly exceeds current forecasts. Without the CHPE project in service or other offsetting changes or solutions, the reliability margins continue to be deficient for the ten-year planning horizon. In addition, while CHPE is expected to contribute to reliability in the summer, the facility is not expected to provide any capacity in the winter.

I am uncomfortable that there is this much reliance on a single project to address the problems identified.  I discussed the start of construction late last year for the Champlain Hudson Power Express (CHPE) project.  It is a 339-mile underground transmission line capable of bringing 1,250 MW from the Province of Quebec to Astoria Queens in New York City.  I explained that I was worried about the schedule and costs of the project.  The NYISO Resource Adequacy analyses must necessarily rely on the developer’s prediction for completion.  Richard Ellenbogen and I share the timeliness concern.  Richard noted that the project was proposed in 2011 and the PSC authorized it on 4/18/13.  It has been 11.5 years since it was proposed, 9.5 years since it was authorized, and construction started a year after the funding contract was signed.  In addition, it has recently come out that landowners on sections of the right-of-way that are on land have just been informed that they will be impacted.  The likelihood of additional delays seems high.  Given that other renewable projects are being re-evaluated because of price increases due to inflation and increased cost of materials it seems that this project will also have the same problems.  Given its importance to New York City reliability, I cannot conceive of any scenario in which the State will not grant any cost overruns requested by the developers. This project is already expensive equating to an estimated increase in customer electric bills of 2.1 – 4.1% (or $2.08 – $4.08 per month for the average residential customer.  I am confident that at the end of the day the final costs will be much higher.

The STAR quarterly report did not limit its analysis to just New York City.

In addition to New York City, this assessment also evaluated the transmission security margins for the statewide system as well as Lower Hudson Valley and Long Island localities. For these localities, the planned Bulk Power Transmission Facilities (“BPTF”) through the study period are within applicable reliability criteria based on the baseline summer coincident peak demand forecast with expected weather and with the planned projects meeting their proposed in-service dates. The NYISO assessed the resource adequacy of the overall system and found no resource adequacy reliability needs.

The NYISO is a product of the de-regulated New York electric system.  As such they are ardent supporters of “market” solutions.  This adds a layer of uncertainty because NYISO must develop some sort of incentive for a developer to provide the necessary resources.  If it was an attractive investment, then I would expect that someone would already be developing the necessary resources.  In addition, Con Ed must also determine if local transmission upgrades can resolve the problem.

The short-term need observed in 2025 is a Near-Term Reliability Need. As a result, solutions will be solicited, evaluated, and addressed in accordance with the NYISO Short-Term Reliability Process. The need arises within the Con Edison Transmission District; therefore, Con Edison is the Responsible Transmission Owner for developing a regulated solution.(Reference NYISO’s Open Access Transmission Tariff Section 38.3.6)

The report identifies another particular issue that illustrates why regular STAR analyses are required and why this issue is coming up now.  Although all the affected parties may know that there will be changes to the system and have reasonable expectations what they will be, the NYISO cannot officially act until certain filings are made.

Central Hudson identified transmission security issues in its transmission district on its non-BPTF system. These are primarily driven by the assumed unavailability of certain generation in its district affected by the Peaker Rule. Given that those generators have not yet provided complete Generator Deactivation Notices to the NYISO, the local non-BPTF criteria violations identified by Central Hudson are being provided for information but were not assessed to identify possible Generator Deactivation Reliability Needs at this time.

The report also describes an upcoming issue that will be considered officially in a subsequent report. The “informational scenario” considers interconnecting large loads:  the Micron New York semiconductor manufacturing (530 MW in 2030), the Air Products and Chemicals (Q#1446), and other load changes that increase load another 694 MW.

As an informational scenario, this STAR includes an evaluation of the impact of additional large load interconnection projects primarily in western and central New York. The anticipated increases to the demand forecast due to these large loads in 2025 is 764 MW which results in a corresponding reduction to the available margin, such that in 2025 the statewide system margin is projected to be deficient of 145MW. By 2033, additional large loads increase the demand by 1,224 MW which results in a corresponding deficient margin of 104 MW. If CHPE does not begin operation, the state wide system margin is projected to be deficient for all years 2025 through 2033 when considering the additional large loads. The 2023 Quarter 3 STAR will include these load projects and the associated system margin impacts. The solution to the New York City reliability need identified in this STAR may also address the state wide system margin concern.

The Executive Summary summarizes their approach:

The wholesale electricity markets administered by the NYISO are an important tool to help mitigate these risks. The markets are designed, and continue to evolve and adapt, to send appropriate price signals for new market entry and the retention of resources that assist in maintaining reliability. The potential risks and resource needs identified in the NYISO’s analyses may be resolved by new capacity resources coming into service, construction of additional transmission facilities, and/or increased energy efficiency and integration of demand-side resources. The NYISO is tracking the progression of many projects that may contribute to grid reliability, including numerous offshore wind facilities that have not yet met the inclusion rules for reliability assessments. The NYISO will continue to monitor these resources and other developments to determine whether changing system resources and conditions could impact the reliability of the New York bulk electric grid.

Note that there are three ways the problem identified can be resolved: building new capacity resources, construction of additional transmission facilities, and/or reducing load expectations with increased energy efficiency and integration of demand-side resources.  Even if the Hochul Administration came to its senses and decided to facilitate the construction of dependable generating capacity, that is to say, fossil-fired generators, there is no way that any generating resource to support reliability could get built in this timeframe.  My rule of thumb for just getting permits in New York City is a minimum of three years.  The summer of 2025 is only two years away.  Of course, the possibility of any new fossil infrastructure is very unlikely anyway.  Designing, permitting, and building additional transmission facilities may not take quite as long but I cannot imagine this solution could be available in two years.  There already are great expectations for reducing load so I cannot imagine any scenario that could reduce additional load on the order necessary to meet the identified load shortfall.

The final paragraph in the Executive Summary describes the specific filings that will trigger further STAR revisions.

As generators that are subject to the DEC’s Peaker Rule submit their Generator Deactivation Notices, the NYISO and the responsible Transmission Owners will continue to evaluate in future STARs whether Generator Deactivation Reliability Needs arise from the deactivation of Initiating Generators. (Reference NYISO’s Open Access Transmission Tariff Section 38.1 state that an “Initiating Generator” is “a Generator with a nameplate rating that exceeds 1 MW that submits a Generator Deactivation Notice for purposes of becoming Retire or entering into a Mothball Outage or that has entered into an Installed Capacity (ICAP) Ineligible Forced Outage pursuant to Section 5.18.2.1 of the ISO Services Tariff which action is being evaluated by the ISO in accordance with its Short-Term Reliability Process requirements in this Section 38 of the ISO Open Access Transmission Tariff.

Discussion

The Findings section expands the description of the problem found.  Without changes to existing load pattern the summer peak load demand in New York City would be “deficient by 306 MW in 2025 for a duration of 7 hours”.  There are uncertainties in the load demand forecasts.  Assuming the upper bound of “demand under baseline weather conditions (95 degrees Fahrenheit) in 2025 results in a deficiency of 446 MW over 9 hours.” If the weather is hotter or lasts for an extended period the “deficiency would be significantly greater.” This exemplifies the tradeoffs the NYISO and NYSRC must make when assessing resource adequacy and reliability standards.  If the deficiency is “significantly greater” then it will be impossible to manage the load without rolling blackouts.

The NYISO writes: “The deficient margin is primarily due to the increased demand forecasts within New York City combined with the planned unavailability of simple-cycle combustion turbines to comply with the DEC’s Peaker Rule in 2025”.   Apparently, it is not politically correct to point out that Hochul Administration’s policy that finalized the shutdown of 2,000 MW of nuclear power and the disapproval of a plan to build a 1,040 MW, eventually reduced to 437 MW, combined cycle facility exacerbated this problem and that if those resources were available there would not be a problem.

As it stands now, I expect that the solution will be an extension of the operating permits for the peaking turbines because there is no other viable solution to maintain reliability.

The NYISO describes the process and explains how it will be resolved in the following figure.  They have identified the reliability need.  They will ask Consolidated Edison if the problem can be resolved with transmission system revisions in Step 2.  At the same time in Step 3, NYISO will solicit  market-based solutions from other developers.  In the next step NYISO reviews the proposed solutions “to determine if they are viable and sufficient to address the identified need.”  The NYISO description of the last step notes:

Timing is an essential component of the NYISO’s evaluation. If proposed solutions are not viable or sufficient to meet the identified reliability need, interim solutions must be in place to keep the grid reliable. One potential outcome could include relying on generators that are subject to the DEC’s Peaker Rule to remain in operation until a permanent solution is in place. The DEC’s Peaker Rule anticipated this scenario when it authorized the NYISO to designate certain units to remain in operation beyond 2025 on an as-needed basis for reliability. Based on findings from its Short-Term Reliability Process, the NYISO may designate certain units, in sufficient quantity, to remain in operation for an additional two years (until May 1, 2027) with the potential of an additional two-year extension (to May 1, 2029) if a permanent solution that is needed to maintain reliability has been selected but is not yet online. The NYISO would only temporarily retain peakers as a last-step approach if it does not expect solutions to be in place when the identified reliability need is expected in 2025.

Reaction

Utility Dive described the report.  Their article quotes Zach Smith, vice president of system and resource planning for the NYISO as saying the assessment “reflects the extraordinary challenges of the grid in transition.”  It also notes that the report acknowledges “uncertainty” in the demand forecast surrounding assumptions including population and economic growth, the proliferation of energy efficiency, the installation of behind-the-meter renewable energy resources, and EV adoption and charging patterns.

The reaction of parties in New York State was predictable.  Marie French writing at Politico solicited comments from the Hochul Administration:

“To be clear: The reliability of our grid is not in question,” Hochul spokesperson Katy Zielinski said in a statement. “We are committed to ensuring New Yorkers have a reliable and affordable power supply — and we can do this while accomplishing our nation-leading climate goals. Governor Hochul remains fully committed to rapidly decreasing emissions and setting an example for how clean energy and reliability can go hand-in-hand.”

French said that Zielinski cited the planned Canadian hydropower line, the Clean Path line and offshore wind projects as ways to bring more renewables into New York City.   There is a fundamental issue with these projects because they all rely heavily on distant  transmission that is overly vulnerable to outages  One of the New York City blackouts occurred because a transmission line into the city went down and in-city generation could not be brought up fast enough to react to the loss of energy supply.  There are specific reliability rules in place that mandate a minimum capability of in-city generation when storms threaten transmission lines into the City.  I am not sure how this will be addressed in the future.  The Canadian hydropower line may not be affected by storms but still could go down unexpectedly for other reasons.  The Clean Path project is “is comprised of more than 20 renewable energy generation projects and an approximate 175-mile, underground transmission line.  I am guessing that the argument is that an underground line can provide power that is not subject to storm outages so is exempt from the transmission line reliability rule.   However, even if they are much less likely to go out, when they do have problems fixing them is much more difficult.  Counting on offshore wind as a viable replacement in the City is very risky unless it is coupled with sufficient energy storage to cover the energy needs for an entire heat wave because the meteorological conditions that cause extreme heat are associated with high-pressure systems that also have light winds.

The Peak Coalition has been the primary mover for peaking power plant environmental justice.  French mentioned their statement that notes:

PEAK Coalition is gravely concerned with the impact that the reliability deficit estimated in the Short-Term Assessment of Reliability (STAR) report for Q2 of 2023 released by the New York Independent Systems Operator (NYISO) will have on communities that live near power plants. We encourage all stakeholders involved in the energy planning process to take concrete action to prevent delaying the closure of fossil fuel peaker plants in 2025 and beyond.  These plants harm the communities that surround them every hour that they operate. PEAK refuses to accept a scenario in which environmental justice communities must suffer further harm to guarantee further profligate summertime energy consumption in commercial buildings and wealthy communities.

I have evaluated the EJ claims.  The PEAK coalition has stated that “Fossil peaker plants in New York City are perhaps the most egregious energy-related example of what environmental injustice means today.”  The influence of this position on current New York State environmental policy has led to this issue finding its way into multiple environmental initiatives. However, the presumption of egregious harm is based on selective choice of metrics, poor understanding of air quality health impacts,  and ignorance of air quality trends.  

As noted previously the NYISO is invested in market solutions. French also got a statement from the NYISO that is completely consistent with that approach:

“We’ve identified the reliability need, so we’re confident that’s present for summer 2025,” said NYISO spokesman Kevin Lanahan. “We’re also confident that we can solve the reliability [need]. That’s the nature of our planning process, to identify those issues with enough time to solve the problems so we’re confident we can find the solution and keep the system reliable.”

French also got a statement from Gavin Donohue at the Independent Power Producers:

“The pace of play is not keeping up with pace of promises, and this report makes that clear,” said Independent Power Producers of New York president and CEO Gavin Donohue, who represents the state’s existing nuclear, renewable and predominantly fossil fuel power plants. “This report should draw attention from state officials in shaping realistic public policies. I encourage the NYISO to identify solutions that are market-based so we can set ourselves on the pathway to a cleaner energy future, while maintaining the reliability of our grid at affordable rates.”

James Hanley from the Empire Center summarizes the implications well.  He concludes:

The mistake New York has made is not its goal to eventually reduce NOx emissions but its rush to shut down the peakers — and Indian Point — before developing reliable replacement sources of power. Notably, the Department of Environmental Conservation rejected proposals by NRG Energy to update nearly 1,000 megawatts of electricity production in the city to newer, cleaner-burning, and NOx-standard compliant combined-cycle power plants, claiming that NRG “failed to demonstrate the need or justification for the proposed project.”

This “shutdown first, replace later” model was a major cause of rolling blackouts on the West Coast, but New York authorities didn’t bother to learn from California’s experience. Simple common sense would indicate that the wise approach would be to find assured sources of reliable and dispatchable electricity production before taking critical power plants offline. Sadly, common sense was the first victim of New York energy policy. Even more sadly, it won’t be the last.

Conclusion

Despite assurances from Hochul spokesperson Katy Zielinski, the reliability of the New York City grid is in question. The plans rely on resources that are new to New York and that increases uncertainty.  Presuming that proposed projects will replace operational facilities on the schedule proposed is very risky. 

There is another dynamic here that will be interesting to watch.  Peaker power plants are a primary scapegoat for the New York City EJ community.  The PEAK Coalition has already gone on record stating that “If NYISO is forced to issue reliability-must-run orders, New Yorkers will know that electric utilities and state governments willingly failed to act to protect communities most impacted by fossil fuel emissions and climate change”.  The electric utilities and state government have failed to explain the potential impacts to the disadvantaged communities if fossil-fired peaking units are not replaced with proven technology.  The risks to those communities imposed by the presence of such resources are not nearly as large as the risks to those communities from blackouts.  Keeping the lights on is the better social choice.

Thanks to Russell Schussler for review and helpful comments.  Any technical errors are mine.

Author: rogercaiazza

I am a meteorologist (BS and MS degrees), was certified as a consulting meteorologist and have worked in the air quality industry for over 40 years. I author two blogs. Environmental staff in any industry have to be pragmatic balancing risks and benefits and (https://pragmaticenvironmentalistofnewyork.blog/) reflects that outlook. The second blog addresses the New York State Reforming the Energy Vision initiative (https://reformingtheenergyvisioninconvenienttruths.wordpress.com). Any of my comments on the web or posts on my blogs are my opinion only. In no way do they reflect the position of any of my past employers or any company I was associated with.

One thought on “NYISO Short-Term Assessment of Reliability July 2023”

Leave a comment