New York Energy Burden Definition

I worry that the implementation of New York’s Climate Leadership & Community Protection Act (Climate Act) is going to increase the cost of energy to those least able to afford it.  New York State does not have a clearly defined affordability threshold for the Climate Act nor does it track energy burden metrics.  The only metric referenced in the Climate Act Scoping Plan is a Public Service Commission target energy burden set at or below 6 percent of household income for all low-income households in New York State.  This post addresses that metric.

I have followed the Climate Act since it was first proposed, submitted comments on the Climate Act implementation plan, and have written over 350 articles about New York’s net-zero transition.  I have devoted a lot of time to the Climate Act because I believe the ambitions for a zero-emissions economy embodied in the Climate Act outstrip available renewable technology such that the net-zero transition will do more harm than good by increasing costs unacceptably, threatening electric system reliability, and causing significant unintended environmental impacts.  The opinions expressed in this post do not reflect the position of any of my previous employers or any other organization I have been associated with, these comments are mine alone.

Climate Act Background

The Climate Act established a New York “Net Zero” target (85% reduction and 15% offset of emissions) by 2050.  It includes an interim 2030 reduction target of a 40% reduction by 2030 and a requirement that all electricity generated be “zero-emissions” by 2040. The Climate Action Council is responsible for preparing the Scoping Plan that outlines how to “achieve the State’s bold clean energy and climate agenda.”  In brief, that plan is to electrify everything possible using zero-emissions electricity. The Integration Analysis prepared by the New York State Energy Research and Development Authority (NYSERDA) and its consultants quantifies the impact of the electrification strategies.  That material was used to develop the Draft Scoping Plan.  After a year-long review, the Scoping Plan recommendations were finalized at the end of 2022.  In 2023 the Scoping Plan recommendations are supposed to be implemented through regulation and legislation. 

Renewable Energy Program Affordability Concerns

Proponents of the Climate Act don’t acknowledge that there is a affordability safety valve.  New York Public Service Law  § 66-p (4). “Establishment of a renewable energy program” includes constraints for affordability and reliability that could be used to limit the damage of Climate Act implementation.  § 66-p (4) states: “The commission may temporarily suspend or modify the obligations under such program provided that the commission, after conducting a hearing as provided in section twenty of this chapter, makes a finding that the program impedes the provision of safe and adequate electric service; the program is likely to impair existing obligations and agreements; and/or that there is a significant increase in arrears or service disconnections that the commission determines is related to the program”. 

There are affordability considerations regarding the constraint “significant increase in arrears or service disconnections”.  I believe that the Hochul Administration’s Climate Action Council should define what that means.  For example, Addressing Energy Poverty in the US offers possible criteria:

According to the U.S. Department of Energy, the average energy burden for low-income households is 8.6%. That is three times higher than for non-low income households, which is about 3%.  And according to the Kleinman Center for Energy Policy at University of Pennsylvania, more than one-third of US households are experiencing “energy poverty,” having difficulty affording the energy they need to keep the lights on and heat and cool their home. 

I think that New York should define its energy poverty targets and track them.  Once the standard is defined, the status of the standard in New York should be monitored and made publicly available, and a threshold for acceptability established.  For example, if the New York state low-income standard is 8.6% and the baseline energy burden level is 9%, then if the average energy burden increases to 10% provisions to temporarily suspend or modify the obligations should be triggered. 

In order to implement my recommendation, the first task would be to establish the energy burden standard.  As far as I can determine there is only one existing candidate.  The Public Service Commission has a target energy burden set at or below 6 percent of household income for all low-income households in New York State.  Reviewing it raises questions about its suitability for this purpose.

Order Adopting Low Income Program Modifications and Directing Utility Filings

The six percent target was included as part of Public Service Commission (PSC) Case Number: 14-M-0565, the Proceeding on Motion of the Commission to Examine Programs to Address Energy Affordability for Low Income Utility Customers.  According to the PSC: “The primary purposes of the proceeding are to standardize utility low-income programs to reflect best practices where appropriate, streamline the regulatory process, and ensure consistency with the Commission’s statutory and policy objectives.”  On May 20, 2016 the Order Adopting Low Income Program Modifications and Directing Utility Findings adopted “a policy that an energy burden at or below 6% of household income shall be the target level for all 2.3 million low income households in New York.” 

The order notes that:

There is no universal measure of energy affordability; however, a widely accepted principle is that total shelter costs should not exceed 30% of income. For example, this percentage is often used by lenders to determine affordability of mortgage payments. It is further reasonable to expect that utility costs should not exceed 20% of shelter costs, leading to the conclusion that an affordable energy burden should be at or below 6% of household income (20% x 30% = 6%). A 6% energy burden is the target energy burden used for affordability programs in several states (e.g., New Jersey and Ohio), and thus appears to be reasonable. It also corresponds to what U.S. Energy Information Administration data reflects is the upper end of middle- and upper-income customer household energy burdens (generally in the range of 1 to 5%). The Commission therefore adopts a policy that an energy burden at or below 6% of household income shall be the target level for all low-income customers.  The policy applies to customers who heat with electricity or natural gas. 

The energy burden statistics cited in the Staff Report suggest a significant energy divide exists for low-income households. About 2.3 million households are at or below 200% of FPL, with an energy affordability “gap,” i.e., an average annual energy burden above the 6% level.  Approximately 1.4 million of these households receive a HEAP benefit; however, for the 2013-2014 program year, only about 316,000 of those households received a benefit for utility service.

The Order notes that reducing this energy burden will be a challenge:

Closing such a wide gap for 2.3 million low-income households is a non-trivial pursuit, and will require a comprehensive effort that involves all of the tools at the state’s disposal, including, but not limited to, utility ratepayer-funded programs. A central role in achieving energy affordability for low income customers is played by the financial assistance programs administered by the Office of Temporary and Disability Assistance (OTDA), including the Home Energy Assistance Program (HEAP). Another important role is played by low income energy efficiency programs such as the Weatherization Assistance Program administered by New York State Homes and Community Renewal (HCR) and the ratepayer–funded EmPower-NY program administered by the New York State Energy Research and Development Authority (NYSERDA). Utility ratepayer funded programs also include the rate discount programs under discussion here, as well as investments designed to create opportunities for low income households to benefit from the cost savings offered by Distributed Energy Resources.

The Order goes on to offer suggestions to close the gap.  It argues that a holistic approach among many state agencies is needed.  For that to work there must be better coordination “among the various governmental and private agencies” that address this issue.  The Order suggests that “achieving an optimal design will require building new partnerships and new mechanisms for identifying and enrolling eligible households”. 

The most tangible aspect of the Order to address the energy burden problem was to establish low-income bill discount programs for each of the major electric and gas utilities. This included standardization of utility energy affordability programs statewide to “reflect best practices where appropriate, streamlining of rate cases, and greater consistency between the programs and the Commission’s statutory and policy objectives.” 

On Augst 13, 2021 a press release describing the expansion of the low-income affordability program noted:

To reach the target of no more than a 6 percent energy burden for low-income New Yorkers, it would be necessary to coordinate and leverage all available resources at the State’s disposal, including multiple sources of financial assistance to lower customers’ bills, energy efficiency measures to reduce usage, and access to clean energy sources to lower the cost of the energy itself. As part of the Commission’s decision, Commission staff will work closely with other entities, including OTDA and the utilities, to ensure that low-income customers receive the assistance they need.

The utility companies submit quarterly reports documenting the number of low-income customers receiving discounts and the amount of money distributed.  However, I have been unable to find any documentation describing how many customers meet the 6% energy burden criteria, much less any information on how those numbers are changing.  The biggest problem with this energy burden program is that it only applies to electric and gas utility customers.  Citizens who heat with fuel oil, propane, or wood are not covered.

Sc=oping Plan Energy Burden

The only reference in the Scoping Plan to the PSC low-income energy burden target of 6% was in Appendix A, the Enabling Initiative #7 slide in the Power Generation Advisory Panel Considerations.  The relevant sentence states a potential barrier to success is “The State’s ability to project how much financial support will be adequate while assuring that low-income customers will not surpass the 6% energy burden during the transition to electrification”.   As noted previously, this ignores citizens who do not heat with electricity or natural gas.

I am aware of only one other suggestion for an affordability metric.  In the 2021-2022 legislative session there was a proposal that included a requirement for state agencies to identify policies to ensure affordable housing and affordable electricity using an “affordability of electricity” metric that was defined as “electricity  does not cost more than six percent of a residential customer’s  income.” 

I don’t think either is the appropriate metric for the Climate Act transition.  The legislative proposal only addresses electricity and the PSC energy burden target only addresses only utility bills.  This fails to address the concerns of citizens who heat their homes with fuels not provided by a utility such as heating oil or propane.  The Climate Action Council has proposed a cap-and-invest program that will put a price on gasoline and diesel fuels.  Those should also be considered part of the energy burden.

Reality Disconnect

The Order Adopting Low Income Program Modifications narrative on the clean energy transition is inconsistent with the experience of every jurisdiction that has tried to replace existing sources of electrical generation with wind, solar, and storage. The total costs to integrate intermittent and diffuse wind and solar inevitably increase costs.  The argument in the Order claims:

In addition, the best solution for all customers, including low income, lies in facilitating opportunities to invest in clean energy and the means to reduce energy costs. Greater access and support for low income and underserved communities to Distributed Energy Resources is the best way to narrow the affordability gap that needs to be filled with direct financial assistance for customers with low incomes. Greater access to advanced energy management products to increase efficiency for low-income customers will empower those for whom these savings may have the greatest value, as well as allowing the most disadvantaged customers more choice in how they manage and consume energy.

There are two aspects to the claim that clean energy will reduce energy costs that are problems.  The first problem is the cost of new generating capacity in general.  The New York State Energy Research & Development Authority recently announced that investments in three offshore wind and 22 land-based renewable energy projects totaling 6.4 gigawatts.  For the offshore wind projects “the average bill impact for customers over the life of the projects will be approximately 2.73 percent, or about $2.93 per month.”  For the other projects the average bill impact for customers over the life of the projects will be approximately 0.31 percent, or about $0.32 per month.  If future projects somehow stay at the same price despite the costs of inflation, supply chain issues, and all the other reasons that developers for existing projects recently argued when calling for renegotiation of their project contracts, then the average monthly bill impacts will be $16.40 per month for the projected offshore wind, onshore wind, and solar capacity needed in 2030.  That is just the cost of additional generating capacity and does not include the energy storage needed to address intermittency or transmission upgrades needed to address diffusivity.   The Order’s claim that clean energy will reduce energy costs is unsupportable.

The second problem is that those additional costs necessitate changes to low-income customer support.  In order to maintain the same relative level of energy burden more money will be required for these higher costs.  Furthermore, the higher costs will mean more people will qualify for energy burden support.  That additional money must be covered by the remaining ratepayers, driving their costs higher, and increasing the number of people that quality for energy burden support.  At some point this spiral of costs will become unsustainable.

Conclusion

Increased energy costs are regressive taxes and impact those least able to afford them the most.  I believe that the net-zero transition will inevitably increase energy costs.  Surely there is a point when the costs are unaffordable overall or the impacts to low-income ratepayers are unacceptable. 

I believe it is necessary to establish a energy burden standard. The first step to address this problem is to develop a transparent metric for energy burden.  The Public Service Commission target energy burden of 6 percent of household income only applies to utility costs.  A metric that considers all energy costs including transportation has to be developed.  The second step would be to establish energy burden acceptability criteria that could be used to comply with the New York Public Service Law  § 66-p (4) affordability considerations associate with the constraint “significant increase in arrears or service disconnections”.  Finally, a transparent and readily available tracking system needs to be established.

Clearly there is a reluctance by any of the politicians supporting the clean energy transition to be accountable for costs.  There is an existing energy burden metric but the status of ratepayers relative to the 6 percent metric is not documented.  It is almost as if the State does not want us to know where we stand.  As such, the possibility of properly tracking energy poverty is unlikely.  I think that is to the great shame of the proponents of the clean energy transition.

New Climate Reality is Passing New York By

Note: For quite a while now I have put my Citizens Guide to the Climate Act article as the top post on the website because it summarizes the Climate Leadership & Community Protection Act (Climate Act). This post updates my current thoughts about the Climate Act and will replaces that post at the top of the list of articles on October 2, 2023

There is a new climate reality and it is passing New York by.  New York decision makers are going to have to address the new reality that proves that the Hochul Administration’s Scoping Plan to implement the Climate Act will adversely affect affordability, reliability, and the environment.  This post highlights articles by others that address my concerns.

I have followed the Climate Act since it was first proposed, submitted comments on the Climate Act implementation plan, and have written over 350 articles about New York’s net-zero transition.  I have devoted a lot of time to the Climate Act because I believe the ambitions for a zero-emissions economy embodied in the Climate Act outstrip available renewable technology such that the net-zero transition will do more harm than good by increasing costs unacceptably, threatening electric system reliability, and have major unintended environmental impacts.  The opinions expressed in this post do not reflect the position of any of my previous employers or any other company I have been associated with, these comments are mine alone.

Climate Act Background

The Climate Act established a New York “Net Zero” target (85% reduction and 15% offset of emissions) by 2050.  It includes an interim 2030 reduction target of a 40% reduction by 2030 and a requirement that all electricity generated be “zero-emissions” by 2040. The Climate Action Council is responsible for preparing the Scoping Plan that outlines how to “achieve the State’s bold clean energy and climate agenda.”  In brief, that plan is to electrify everything possible using zero-emissions electricity. The Integration Analysis prepared by the New York State Energy Research and Development Authority (NYSERDA) and its consultants quantifies the impact of the electrification strategies.  That material was used to develop the Draft Scoping Plan.  After a year-long review, the Scoping Plan recommendations were finalized at the end of 2022.  In 2023 the Scoping Plan recommendations are supposed to be implemented through regulation and legislation. 

Climate Science

In the past several weeks there have been multiple articles highlighting issues that call into question the rationale for the Climate Act and Climate Act net-zero transition.   The rationale for the Climate Act is that there is an existential threat due to climate change.  However, the Epoch Times reports that is not a universally held position:

There’s no climate emergency. And the alarmist messaging pushed by global elites is purely political. That’s what 1,609 scientists and informed professionals stated when they signed the Global Climate Intelligence Group’s “World Climate Declaration.”

The article gives a good overview of the World Climate Declaration.  The declaration’s signatories include Nobel laureates, theoretical physicists, meteorologists, professors, and environmental scientists worldwide. The article quotes a few signatories who when asked by The Epoch Times why they signed the declaration stating that the “climate emergency” is a farce, they all stated a variation of “because it’s true.” 

In my case, I signed the Declaration because I do not think we understand natural climate variability well enough to be able to detect the effect of a relatively small change to the atmosphere’s radiative budget caused by mankind’s greenhouse gas (GHG) emissions.  There are so many poorly understood factors at play and the mathematical challenges of simulating the chaotic, non-linear processes are so immense that I think that claiming that Global Climate Models can simulate the atmosphere well enough to make major changes to the energy system of the world is absurd.

There is another important aspect.  One of the key points made in the Declaration is that climate science is overly politicized:

“Climate science should be less political, while climate policies should be more scientific,” the declaration begins. “Scientists should openly address uncertainties and exaggerations in their predictions of global warming, while politicians should dispassionately count the real costs as well as the imagined benefits of their policy measures.”

It seems to me that every day there is another mass media story attributing any extreme weather event to climate change and insinuating that the “science” has unequivocally shown that there is a link to mankind’s GHG emissions has made the weather more extreme.  The fact is that the latest research and the Intergovernmental Panel on Climate Change are finding that as Roger Pielke, Jr. explains the “projected climate futures have become radically less dire”.  He argues that the consensus has accepted a large change in expected warming due to a doubling of GHG emissions — from 4oC to 2.5oC or less.   Pielke notes that he has documented this trend  for years and has “been talking about the incredible shift in expectations for the future” recently.  Unfortunately he also notes: “Despite the growing recognition that our collective views of the future have changed quickly and dramatically, this change in perspective — a positive and encouraging one at that — has yet to feature in policy, media or scientific discussions of climate.”   He concludes “That silence can’t last, as reality is persistent.”

Affordability

I think this is the one issue that might force political change to the Climate Act net-zero transition.  A coalition of business organizations have called for a “reassessment” of how the Climate Act is being implemented highlighting current policies to determine “what is feasible, what is affordable and what is best for the future of the state.”  In response, Department of Environmental Conservation Commissioner Basil Seggos told Capital Tonight that “the costs of inaction are much higher.”  He goes on: “Listen, we know from two years of very intensive research that the cost of inaction on climate in New York far exceeds the cost of action by the tune of over $100 billion”I disagree.

The Scoping Plan that documents this claim by Seggos has been described as “a true masterpiece in how to hide what is important under an avalanche of words designed to make people never want to read it”.  No where is this more evident than in the tortuous documentation for this cost claim.  I documented the issues with costs and benefits in my  comments (social cost of carbon benefits, Scoping Plan benefits, and electric system costs).  In brief, the Hochul Administration has never provided concise documentation that includes the costs, expected emission reductions and assumptions used for the control strategies included in the Integration Analysis documentation making it impossible to verify their assumptions and cost estimates. 

The claim that the costs of inaction are more than the costs of action compares real costs to New Yorkers relative to societal benefits that can be charitably described as “biased high” or more appropriately “cherry picked” to maximize alleged benefits and, more importantly, do not directly offset consumer costs.  The benefits claimed are also poorly documented, misleading and the largest benefit is dependent upon an incorrect application of the value of carbon.  The plan claims $235 billion societal benefits for avoided greenhouse gas emissions.  I estimate those benefits should only be $60 billion.  The Scoping Plan gets the higher benefit by counting benefits multiple times.  If I lost 10 pounds five years ago, I cannot say I lost 50 pounds but that is what the plan says.  The cost benefit methodology was duplicitous because the cost comparisons were relative only to Climate Act requirements that did not include “already implemented” programs.  For example, this approach excludes the costs to transition to electric vehicles because that was a requirement mandated before the Climate Act.  I maintain that the total costs to transition to net-zero should be provided because that ultimately represents total consumer costs.  

It is also frustrating that the State ignores that other jurisdictions are finding costs are an issue.  In a recent article I noted that the Prime Minister of Great Britain, Rishi Sunak, said he would spare the public the “unacceptable costs” of net zero as he scaled back a string of flagship environmental policies. The fact is that every jurisdiction that has tried to transition away from fossil-fueled energy has seen a significant increase in consumer costs.  For example, Net Zero Watch recently published a report that describes six ways renewables increase electricity bills that makes that inevitable.   The article explains:

In order to reduce bills, a new generator generally has to force an old one to leave the electricity market — otherwise there are two sets of costs to cover. But with wind power, you can’t let anything leave the market, because one day there might be no wind.

The article goes on to explain that as well as adding excess capacity to the grid, renewables also have a series of other effects, each of which will push bills up further:

Renewables need subsidies, they cause inefficiency, they require new grid balancing services that need to be paid for; the list of all the different effects is surprisingly long. There is only one way a windfarm will push your power bills, and that’s upwards.

Reliability

Another flawed aspect of the Climate Act narrative is that a transition to a zero-emissions electric system is straight-forward and there are no significant technological challenges.  Terry Etam summed up the issues evident in the German transition that will also occur in New York.  In an article about the ramifications of the energy requirements for implementing artificial intelligence applications, he argued that the fossil-fired energy growth in the developing nations has been discouraged by the G7 nations.  However, those nations are pushing back on anything that is not in their best interests.  He writes:

The second big tectonic shift was on full display at the recent G20 summit. The African Union was admitted as a member, which was kind of a big deal, particularly for Africa, but also for the world in general. The addition acknowledges that other voices need to be on the world stage, a sense of humility the G7 has long lacked. The final communique issued at the end of the G20 summit included doses of common sense lacking from typical utterances of the G7: “We affirm that no country should have to choose between fighting poverty and fighting for the planet…It is also critical to account for the short-, medium-, and long-term impact of both the physical impact of climate change and transition policies, including on growth, inflation, and unemployment.” 

Contrast that with the west’s bizarre self-lobotomization when it comes to energy, as best personified by the entity furthest along the rapid-transition path, Germany: the dwindling economic powerhouse is chained to a green freight train it insists is under control, has shut down nuclear power plants with no low-emissions baseload to replace it, and in a final stunning swan dive to the pavement, is orchestrating the installation of 500,000 heat pumps per year to the grid, which will be in most demand in cold weather and will perform worst in cold weather, and will add a potential 10 gigawatts of cold-weather demand at the very instant the grid is least able to afford it, and for which there is no supply available anyway. A German energy economic university think tank says the additional cold-weather demand could only be met by new gas-fired power plants, which are not being built. In sum: Germany has shuttered its cleanest, most reliable energy; it has or is trying to banish hydrocarbons and replace them with intermittent power; and finally, is hastening adoption of devices that will function very well in 80 percent of conditions when it doesn’t matter much but will fail in a spectacularly deadly way at the point in time when they are needed the very most, because heat pumps will be turned up to 11 at the very time the grid will be the most taxed. German engineering isn’t what it used to be.

In the last several years I have concluded that intermittency of wind and solar is the fatal flaw for that technology.  The most important consideration is the need for energy storage.  Francis Menton writing at the Manhattan Contrarian summarizes energy storage problems in a recent post on a new British Royal Society report “Large-scale energy storage.”  This report suffers from the same problems afflicting the Climate Act Scoping Plan.  Menton explains:

Having now put some time into studying this Report, I would characterize it as semi-competent. That is an enormous improvement over every other effort on this subject that I have seen from green energy advocates. But despite their promising start, the authors come nowhere near a sufficient showing that wind plus solar plus storage can make a viable and cost-effective electricity system. In the end, their quasi-religious commitment to a fossil-fuel-free future leads them to minimize and divert attention away from critical cost and feasibility issues. As a result, the Report, despite containing much valuable information, is actually useless for any public policy purpose.

I believe that the insurmountable problem with energy storage backup for wind and solar is worst-case extremes.  The Royal Society report notes that “it would be prudent to add contingency against prolonged periods of very low supply”.  This contingency is the theoretical dispatchable emissions-free resource that the Integration Analysis, New York State Independent System Operator, New York State Reliability Council, and Public Service Commission in the Order Initiating Process Regarding Zero Emissions Target in Case 15-E-0302 all acknowledge is necessary.  Incredibly, the loudest voices on the Climate Action Council clung to the dogmatic position that no new technology like this resource was necessary and excluded any consideration of a backup plan to address the contingency that a not yet commercialized technology might never become commercially viable and affordable.

If New York State were to embrace nuclear energy, then there might be a chance to significantly reduce GHG emissions without affecting reliability.  Instead, the Scoping Plan placeholder option for this resource is green hydrogen.  Menton describes the hydrogen option proposal in the Royal Society report:

Since hydrogen is the one and only possible solution to the storage problem, the authors proceed to a lengthy consideration of what the future wind/solar/hydrogen electricity system will look like. There will be massive electrolyzers to get hydrogen from the sea. Salt deposits will be chemically dissolved to create vast underground caverns to store the hydrogen. Hydrogen will be transported to these vast caverns and stored there for years and decades, then transported to power plants to burn when needed. A fleet of power plants will burn the hydrogen when called upon to do so, although admittedly they may be idle most of the time, maybe even 90% of the time; but for a pinch, there must be sufficient thermal hydrogen-burning plants to supply the whole of peak demand when needed.

The Scoping Plan proposal is slightly different.  It envisions that the electrolyzers will be powered by wind and solar to create so-called “green” hydrogen.  Menton and I agree that the biggest unknown is the cost.  He raises the following cost issues:

  • How about the new network of pipelines to transport the hydrogen all over the place?
  • How about the entire new fleet of thermal power plants, capable of burning 100% hydrogen, and sufficient to meet 100% of peak demand when it’s night and the wind isn’t blowing.
  • They use a 5% interest rate for capital costs. That’s too low by at least half — should be 10% or more.
  • And can they really build all the wind turbines and solar panels and electrolyzers they are talking about at the prices they are projecting?

It gets worse in New York.  Ideologues on the Climate Action Council have taken the position that “zero-emissions” means no emissions of any kind.  They propose to use the hydrogen in fuel cells rather than combustion turbines because combustion turbines would emit nitrogen oxides emissions.  This adds another unproven “at the scale necessary” technology making it even less likely to succeed as well as adding another unknown cost.  In addition, it ignores that there are emissions associated with the so-called zero-emissions technologies that they espouse.  All they are advocating is moving the emissions elsewhere.

Environmental Impacts

I addressed the implications that the Scoping Plan only considers environmental impacts of fossil fueled energy in my Draft Scoping Plan Comments.  The life-cycle and upstream emissions and impacts are addressed but no impacts of the proposed “zero-emissions” resources or other energy storage technology are considered.  The fact is that there are significant environmental, economic, and social justice impacts associated with the production of those technologies. Furthermore, the most recent cumulative environmental impact analysis only considered a fraction of the total number of wind turbines and area covered by solar PV installations proposed in the Scoping Plan.  As a result, the ecological impacts on the immense area of impacted land and water have not been adequately addressed.

One of the more frustrating aspects of the Hochul Administration’s Climate Act implementation is the lack of a plan.  For example, consider utility-scale solar development.  There are no responsible solar siting requirements in place so solar developers routinely exceed the Department of Agriculture and Markets guidelines for protection of prime farmlands.  My solar development scorecard found that prime farmland comprises 21% of the project area of 18 approved utility-scale solar project permit applications which is double the Ag and Markets guideline. 

I am particularly concerned about environmental impacts associated with Off Shore Wind (OSW).  This will be a major renewable resource in the proposed Climate Act net-zero electric energy system.  The Climate Act mandates 9,000 MW of Off Shore Wind (OSW) generating capacity by 2035.  The Integration Analysis modeling used to develop the Scoping Plan projects OSW capacity at 6,200 MW by 2030, 9,096 MW by 2035 and reaches 14,364 MW in 2040.  I summarized several OSW issues in a recent article that highlighted an article by Craig Rucker titled Offshore Wind Power Isn’t ‘Clean and Green,’ and It Doesn’t Cut CO2 Emissions.  He explains:

A single 12 MW (megawatts) offshore wind turbine is taller than the Washington Monument, weighs around 4,000 tons, and requires mining and processing millions of tons of iron, copper, aluminum, rare earths and other ores, with much of the work done in Africa and China using fossil fuels and near slave labor.

Relying on wind just to provide electricity to power New York state on a hot summer day would require 30,000 megawatts. That means 2,500 Haliade-X 12 MW offshore turbines and all the materials that go into them. Powering the entire U.S. would require a 100 times more than that. 

These numbers are huge, but the situation is actually much worse.

This is because offshore turbines generate less than 40% of their “rated capacity.” Why? Because often there’s no wind at all for hours or days at a time. This requires a lot of extra capacity, which means a lot more windmills will have to be erected to charge millions of huge batteries, to ensure stable, reliable electricity supplies.

Once constructed, those turbines would hardly be earth or human friendly, either. They would severely impact aviation, shipping, fishing, submarines, and whales. They are hardly benign power sources.

The environmental impacts on whales of the OSW resources necessary to meet the net-zero transition are especially alarming.  Earlier this year I described the Citizens Campaign for the Environment virtual forum entitled Whale Tales and Whale Facts.  The sponsors wanted the public to hear the story that there was no evidence that site survey work was the cause of recent whale deaths.  I concluded that the ultimate problem with the forum was that they ignored the fact that construction noises will be substantially different than the ongoing site surveys and will probably be much more extensive when the massive planned construction starts.  The virtual forum noted a lack of funding for continued monitoring necessary to address the many concerns with massive offshore wind development to allay the concerns of the public.   Since then, the Save Right Whales Coalition (SRWC) has found issues with the incidental harassment of whales associated with the noise levels associated sonar surveys done in conjunction with OSW development.  I am very disappointed that the Hochul Administration is not investing in an adequate monitoring program that confirms that whales are not being harmed. 

Conclusion

This article was intended to summarize my current concerns about the impacts of the Climate Act transition on affordability, reliability, and the environment.  There is a growing realization that the alleged problem of global warming is not as big a threat as commonly assumed. Combined with the fact that New York GHG emissions are less than one half of one percent of global emissions and global emissions have been increasing on average by more than one half of one percent per year since 1990 the rationale for doing anything is weak.  It may not mean that we should not do something, but clearly we have time to address the affordability, reliability and environmental impact issues.

The Scoping Plan has not provided comprehensive and transparent cost estimates so New Yorkers have no idea what this will cost.  I explained why the Hochul Administration claim that the costs of inaction are more than the costs of action is misleading and inaccurate.  I believe that all New Yorkers should let it be known that they need to know the expected costs so they can determine if they support the transition.

When the energy system becomes all-electric the reliability of the electric system will be even more critical than today.  The State plan is to proceed as if there are no implementation issues.  The rational thing to do would be to develop demonstration projects to prove feasibility and cost of the new technology needed before dismantling the current system.  Francis Menton explains why this is necessary and how it could work.  There is no sign that is being considered.

It is particularly galling that organizations who claim to be in favor of a better environment have failed to support comprehensive cumulative environmental impact assessment and on-going impact monitoring assessment to potential impacts from wind, solar, and energy storage development on the scale necessary for the net-zero transition.  Maybe they don’t want to know that the concerns are real.

Mark Twain said: “It is easier to fool someone than it is to tell them they have been fooled.”    The politicians who support the Climate Act net-zero transition have been fooled into thinking it is affordable, will not affect reliability, and benefits the environment.  Unfortunately, it is very difficult to slow down, much less stop the unfolding train wreck of these policies.  I encourage readers to keep asking for a full cost accounting of all the proposed programs as the most obvious concern.

Siena College Poll and the Climate Act

A recent Siena College poll found that respondents thought that the cost of living in New York is the top issue for Governor Hochul and the Legislature to address and that threats to the state’s environments was a primary concern for only 4% of the respondents.  This post argues that implementation of New York’s Climate Leadership & Community Protection Act (Climate Act) is inconsistent with the concerns expressed in the poll.

I have followed the Climate Act since it was first proposed, submitted comments on the Climate Act implementation plan, and have written over 350 articles about New York’s net-zero transition.  I have devoted a lot of time to the Climate Act because I believe the ambitions for a zero-emissions economy embodied in the Climate Act outstrip available renewable technology such that the net-zero transition will do more harm than good by increasing costs unacceptably, threatening electric system reliability, and have major unintended environmental impacts.  The opinions expressed in this post do not reflect the position of any of my previous employers or any other company I have been associated with, these comments are mine alone.

Climate Act Background

The Climate Act established a New York “Net Zero” target (85% reduction and 15% offset of emissions) by 2050.  It includes an interim 2030 reduction target of a 40% reduction by 2030 and a requirement that all electricity generated be “zero-emissions” by 2040. The Climate Action Council is responsible for preparing the Scoping Plan that outlines how to “achieve the State’s bold clean energy and climate agenda.”  In brief, that plan is to electrify everything possible using zero-emissions electricity. The Integration Analysis prepared by the New York State Energy Research and Development Authority (NYSERDA) and its consultants quantifies the impact of the electrification strategies.  That material was used to develop the Draft Scoping Plan.  After a year-long review, the Scoping Plan recommendations were finalized at the end of 2022.  In 2023 the Scoping Plan recommendations are supposed to be implemented through regulation and legislation. 

Siena College Poll

According to the press release for a recent Siena College Poll Conducted by the Siena College Research Institute:

More than eight in ten voters say that the cost of living in New York is a major problem – including at least 80% of Democrats, Republicans and independents – and 27%, a plurality, say it is the most important issue that the Governor and Legislature should be working on now. Crime, the recent influx of migrants and the availability of affordable housing are the next three most important issues for New Yorkers. Fifty-seven percent say the quality of life in the state is getting worse, while 27% say it’s staying the same and 14% say it’s getting better, according to a new Siena College poll of registered New York State voters released today.

The poll of 804 New York registered voters was conducted September 10 – 13, 2023.  I spent some time looking at the poll results and think that there are ramifications of this poll on Climate Act implementation.  Consistent with my personal beliefs,  responses to questions about the direction of the state, the fiscal condition of the state, and quality of life were all negative as shown below.

The response to the question “Is New York State on the right track, or is it headed in the wrong direction?” yielded the following results:

               Right track                         35%

               Wrong direction                52%

               Don’t know/No opinion  13%

The question “How would you describe the fiscal condition of New York State right now? Would you describe it as excellent, good, fair, or poor?” generated he following:

               Excellent                             6%

               Good                                    20%

               Total Positive                     26%

               Fair                                      32%

               Poor                                     27%

               Total Negative                  69%

Don’t know/No opinion  5%

The quality-of-life question, “As you consider all aspects of living in New York State, do you think the quality of life in the state is getting better, staying the same, or getting worse?” provided the following responses:

Getting better                                                 14%

Staying the same                                            27%

Getting worse                                                 57%

Vol: Combination (Better and worse)        1%         

Don’t know/Refused                                      2%

In addition to the press release highlighted results, questions related to issues confronting New York were included.  The poll asked respondents whether seven issues were “a major problem for New York State, a minor problem for New York State, or not really a problem for New York State.”  The responses ranked by percentage that thought it was a major problem and including the question number follow

Q27: Cost of living in New York

               Major problem                  83%

               Minor problem                  12%

               Not really a problem        4%

               Don’t know/Refused        0%

Q25: The availability of affordable housing

               Major problem                  77%

               Minor problem                  15%

               Not really a problem        6%

               Don’t know/Refused        1%

Q23: Crime

               Major problem                  75%

               Minor problem                  20%

               Not really a problem        6%

               Don’t know/Refused        2%

Q24: The recent influx of migrants

               Major problem                  62%      

               Minor problem                  22%

               Not really a problem        14%

               Don’t know/Refused        2%

Q28: Access to quality, affordable health care

               Major problem                  52%

               Minor problem                  28%

               Not really a problem        16%

               Don’t know/Refused        4%

Q26: Threats to the state’s environment

               Major problem                  44%

               Minor problem                  34%

               Not really a problem        15%

               Don’t know/Refused        6%

Q29: New Yorkers choosing to leave the state for other parts of the country

               Major problem                  38%

               Minor problem                  25%

               Not really a problem        33%

               Don’t know/Refused        4%

The final question in the poll asked which of these issues “is the single most important issue that the Governor and Legislature should be working on now?”.  The ranked order results:

The cost of living in New York      27%

               Crime                                                 19%

The recent influx of migrants       18%

Affordable housing                          17%

Having access to health care        8%

Threats to the environment          4%

New Yorkers leaving the state      4%

               Something else                                2%

               Don’t know/Refused                       1%

With respect to the Climate Act there are two notable results.  The Climate Act narrative is that there is an existential threat to society due to climate change.  The question concerning threats to the state’s environment found that only 44% agreed that environmental threats was a major problem.  That 49% thought that threats to the state’s environment were either a minor problem or not really a problem is inconsistent with the “existential” threat narrative.  Furthermore, only 4% of respondents thought this was the most important issue for the Governor and Legislature to consider.

The Hochul Administration has not provided clear and transparent costs to ratepayers for expected energy costs nor the costs of electrification of homes and transportation.  All my analyses suggest that the costs to achieve the Climate Act mandates will be extraordinary and there is no question that they will add to the cost of living.  The only issue nearly all respondents responded to was the cost of living in New York and 83% of respondents thought this was a major issue.  This was also the highest ranked of the most important issues questions.

Discussion

There is no question that Climate Act implementation will add to the cost of living in New York.  I recently described expected ratepayer costs due to the New York Climate Act.  James Hanley explained: that multiple offshore wind projects that are not even built yet have asked the state’s Public Service Commission (PSC) to renegotiate their strike prices which will add to costs.  Colin Kinniburgh wrote an article that notes that the renewable energy developers are not in agreement that bailing out struggling projects is appropriate.

In other jurisdictions that are further down the net-zero transition there are concerns.  In the Climate Act, section 16 of § 75-0103, there is a mandate to consider efforts at other jurisdictions: “The council shall identify existing climate change mitigation and adaptation efforts at the federal, state, and local levels and may make recommendations regarding how such policies may improve the state’s efforts.”   Although not expressly noted, I believe that this should extend to other jurisdictions wherever they are.

The Prime Minister of Great Britain, Rishi Sunak, recently said he would spare the public the “unacceptable costs” of net zero as he scaled back a string of flagship environmental policies. A summary of articles about this new position suggests that New York Climate Act implementation plans should pay attention to the lessons learned in Great Britain.  A few highlights follow,

The Daily Telegraph, 20 September 2023 states that:

The Prime Minister warned that voters would revolt against making the UK a net zero carbon emitter by 2050 unless politicians were more honest and “realistic” about the costs involved.

Mr Sunak delayed the ban on new petrol car sales from 2030 to 2035, pushed back the ban on new oil boiler sales from 2026 to 2035, and increased heat pump grants to £7,500.

An editorial in the The Daily Telegraph, 21 September 2023 notes that “Market forces and scientific advancement should create a greener world. We won’t get there by impoverishing Britain and alienating voters”.

The Sun, 21 September 2023 editorializes that:

The Sun launched our Give Us A Brake campaign because we knew the hasty, random, unrealistic climate deadlines he inherited would hurt our readers.

His predecessors had no idea how anyone would afford their headlong charge for net zero and didn’t seem to care.

It was neither fair nor wise to impose vast change without public consent.

This PM’s sensible and modest tweaks deal honestly with reality, not green fantasy and wishful thinking.

Another editorial, The Times, 21 September 2023 states that:

Those disappointed by Rishi Sunak’s sensible decision to delay the deadlines that set the pace of the British economy’s transition to net zero should not blame the prime minister. It was Boris Johnson, playing as statesman as the United Kingdom prepared to host the Cop26 climate summit, who rushed forward by a decade the ban on new petrol and diesel vehicles. It was Theresa May, in the final weeks of her premiership, who led the desultory 90 minutes of parliamentary debate that waved a legally binding 2050 net zero target onto the statute book. Both decisions were symptomatic of a political culture that has persistently failed to reckon with the true costs of a policy that will fundamentally reshape the Britain’s economic landscape.

Those articles provide a backdrop to an essay by Ben Pile that calls the entire Great Britain transition into question.  The essay is a worthwhile read.  He describes six failures of green policy:

  • “No politician has any clue how to realize Net Zero targets.”  This extends to New York because there is no implementation plan just a scoping plan outline.  The failure to include details ensures that the plans will fail.
  • “The green lobby has LONG promised lower prices and greater energy security but has failed to deliver.”  As noted above the New York renewable lobbyists are asking for money before projects even break ground.  Electric reliability issues have been ignored to date by the Climate Action Council.
  • “Behind the scenes, the failure of both global and national climate policy has been known for a long time — since the Paris Agreement (PA) at the latest.”  New York GHG emissions are less than one half of one percent of global emissions and global emissions have been increasing on average by more than one half of one percent per year since 1990.  Why is there any urgency in New York?
  • “Despite claims that other countries are steaming ahead with boiler bans, car bans, heat pumps, and championing Net Zero policies, especially in Europe, they are in fact creating deep schisms between and within EU member states”.  We are starting to see this occur in the United States.
  • “Environmental, Social, and Governance is failing.”  Pile explains that investing using these principles does not provide adequate returns.
  • “ Ukraine, Russia, and the realignment of geopolitics.”  Pile explains that “Who really believes that Western diplomats now have any chance of bringing Russia, China, and India into the Net Zero suicide pact? “

Pile concludes:

Sunak could not have done less to correct this mess. But what he has done is a good thing. And it includes setting a trap for the eco-catastrophists. The more they howl and wail, the more they will expose their utter contempt for ordinary people. It is not in Sunak’s gift, even if he wanted it, to reverse the entire sorry policy agenda. Too much stands in his way. But every scream and tantrum from the blobbers will bring that possibility closer to him or a successor. Because no person with a functioning brain believes that banning the boiler earlier, rather than later, is a good thing. And so the blobbers are set to out themselves, for the duration of this controversy, as brainless ideological zombies. Long may it continue.

Conclusion

The Climate Act narrative is that climate change impacts are pervasive and catastrophic, the primary way to deal with them is not through practical adaptation measures but through policies that reduce greenhouse gas emissions, and the emission reduction strategies will be cheaper because wind and solar are “free”.  I believe that all those beliefs are flawed but have been discouraged because it seems that the media pushes the narrative so much that there is little hope that the net zero transition will be slowed down or stopped.   However, the experience in Great Britain clearly shows that the costs of the net-zero transition are enormous there and will be here too.

The Siena College Research Institute poll showed that despite the relentless climate threat propaganda, the public does not agree that there is an existential threat to society due to climate change.  Most of the respondents to the poll thought that threats to the state’s environment were either a minor problem or not really a problem. Only 4% of respondents thought environmental threats was the most important issue for the Governor and Legislature to consider.  Those results contradict the Climate Act existential threat narrative.

The only issue nearly all respondents responded to was the cost of living in New York and the highest percentage of respondents thought this was a major issue.  This was also the highest ranked of the most important issues questions.  It is obvious from the situation in Great Britain that renewable energy costs will increase the cost of living.   This should make all New York politicians stop to think.

It is not unfair to ask the Hochul Administration to define what is unaffordable, what reliability risks are too great, and which environmental impacts are unacceptable.  This poll offers some hope that if the potential costs are made clear that the politicians will consider pausing implementation until the costs are described completely, the reliability risks addressed, and a cumulative environmental impact assessment of the impacts of all the wind and solar developments that are estimated to be needed by the Scoping Plan is completed. 

Corrected Version – Electric Ratepayer Bills Must Increase Significantly to Meet Climate Act Mandates

This is a correction to an earlier post that consolidates all the recent information on added costs associated with renewable energy development needed to meet Climate Leadership & Community Protection Act (Climate Act) targets that have been authorized or requested.  Dr. Jonathan Lesser found an error that caused the explosive cost increases estimated in the original article.  Although the correct increases are much lower, I still think that these costs are extraordinary albeit not explosive as I said in the original article.

I have been following the Climate Act since it was first proposed, submitted comments on the Climate Act implementation plan, and have written over 350 articles about New York’s net-zero transition.  I have devoted a lot of time to the Climate Act because I believe the ambitions for a zero-emissions economy embodied in the Climate Act outstrip available renewable technology such that the net-zero transition will do more harm than good.  The opinions expressed in this post do not reflect the position of any of my previous employers or any other company I have been associated with, these comments are mine alone.

Climate Act Background

The Climate Act established a New York “Net Zero” target (85% reduction and 15% offset of emissions) by 2050.  It includes an interim 2030 reduction target of a 40% reduction by 2030 and a requirement that all electricity generated be “zero-emissions” by 2040. The Climate Action Council is responsible for preparing the Scoping Plan that outlines how to “achieve the State’s bold clean energy and climate agenda.”  In brief, that plan is to electrify everything possible using zero-emissions electricity. The Integration Analysis prepared by the New York State Energy Research and Development Authority (NYSERDA) and its consultants quantifies the impact of the electrification strategies.  That material was used to develop the Draft Scoping Plan.  After a year-long review, the Scoping Plan recommendations were finalized at the end of 2022.  In 2023 the Scoping Plan recommendations are supposed to be implemented through regulation and legislation. 

Renewable Procurement Background

The NYSERDA is primarily responsible for facilitating projects to meet  Governor Hochul’s target of generating 70 percent of New York State’s electricity from renewable sources by 2030.  For background, I tried to figure out those projects will be funded.  One component is solicitations for large-scale renewables.  That includes a two-step process consisting of:

  1. Step One Eligibility Application: A qualifying step through which the proposer must provide evidence that the Bid Facility is Tier 1 eligible and other general information about the Proposer and the Bid Facility. All Step One Eligibility Applications must be submitted via the RESRFP22-1 solicitation website
  2. Step Two Bid Proposal: A competitive Bid Proposal step, through which NYSERDA will:

a. examine Bid Proposals to determine whether they demonstrate that the Bid Facility and Proposer meet the Minimum Threshold Requirements; and

b. for Bid Proposals that meet those Minimum Threshold Requirements, perform a competitive evaluation based on price and non-price factors.

The focus of this post is on ratepayer costs associated with the zero-emissions mandates.  I did some research on the funding mechanisms and this is how I think renewable energy projects are funded.  The Clean Energy Standard (CES) is the primary method used to “turn New York State’s ambitious clean energy goal into a reality.”  The CES has two mechanisms: the renewable energy standard (RES) and the zero-emissions credit (ZEC) requirement designed to help create a low carbon energy system.  According to NYSERDA:

  • The RES requires every load serving entity (LSE)  in New York State to procure renewable energy certificates(RECs)  associated with new renewable energy resources—known as Tier 1—for their retail customers. If LSEs cannot demonstrate they are meeting the Tier 1 obligation through the possession of RECs, they may make alternative compliance payments (ACPs).
  • The ZEC requirement mandates the LSEs procure ZECs from NYSERDA. The number of ZECs is based on each LSE’s proportionate amount of statewide load, or energy demanded, in a given compliance year.

In addition to these programs, NYSERDA is also advancing offshore wind energy projects through its Offshore Wind Program. NYSERDA also works with its State partners and local communities to rapidly advance new “Build-Ready” projects, prioritizing the development of existing or abandoned commercial sites, brownfields, landfills, former industrial sites, and other abandoned or underutilized sites.

According to NYSERDA:

The Renewable Energy Standard (RES) is a mechanism enacted by the Clean Energy Standard to help New York State reach its ambitious clean energy goals and transition toward a low carbon energy system. The RES requires utilities and other load serving entities in the State to procure Tier 1 renewable energy credits (RECs).

The LSEs must pay for the RECs.  NYSERDA obtains the RECs from developers in auctions.  For example, the 2022 solicitation tried to “procure approximately 4.5 million Tier 1 eligible Renewable Energy Certificates (RECs) from eligible facilities that enter commercial operation on or after January 1, 2015 and on or before May 31, 2025, unless extended to May 31, 2028.”

The costs for the RECs are passed on to consumers in several steps.  First, NYSERDA awards contracts for the RECs to specific projects.  There is no guarantee that a project that has been awarded a contract will actually get built and operate.  The Utility Intervention Unit (UIU), Division of Consumer Protection NYS Department of State recently submitted a petition that noted that “only a tiny subset of awarded projects has completed the entire solicitation cycle and reached operational status (“Operational Projects”)”.   When a project starts to operate, they are awarded RECs which are sold to the LSEs.  The LSEs pass those costs on to their customers only after the PSC authorizes the cost in a utility rate case.

Note, however, that there are other programs described in this article that are also needed to meet the zero-emissions mandate that also add to consumer utility bills.

Informational Report on Ratepayer Costs

The Department of Public Service (DPS) first annual informational report (“Informational Report”) on the implementation of the Climate Act was released in July.  The report is notable because it provided the first Climate Act ratepayer cost estimates provided by the Hochul Administration.  However, those estimates only cover projects that are in the utility rate cases in 2022.   There are many more costs that will eventually show up in electric bills.

The report was based on data submitted by utilities that were collected to pay for Climate Act projects.  The Department of Public Service presentation on the Informational Report noted that “ the estimates of total funding authorized by the Commission to date for various clean energy programs in some instances reflect actions that pre-date the enactment of the Climate Act.”  The conclusion states that the information presented “represents  direct effects of Climate Act implementation only, and only the portion of direct effects of programs over which the Commission has oversight authority.” 

In an earlier post I described Table 4: 2022 Electric CLCPA Recoveries from the report that summarizes costs recovered in 2022 by utilities for electric programs.  The table states that $1,176 million in Climate Act costs were recovered in 2022 and it shows the amount these costs affected utility bills for seven utilities and eight program categories.  I doubt that there are many people who understand what is in each of these different programs but for the purpose of trying to estimate ratepayer costs for renewable energy development we need to summarize the programs.  The CES awards discussed above accounted for $348 million of that total.  The Clean Energy Fund (CEF) “was established as a commitment to clean energy and efficiency measures”.  The latest annual performance report lists four CEF components totaling $500 million: market development, innovation & research, NY-Sun (the distributed solar program), and the NY Green Bank.  The value of distributed energy resources (VDER) also known as the Value Stack is a new mechanism to compensate energy created by distributed energy resources, like residential solar.  The EV Make Ready Program goal is to support the development of electric infrastructure and equipment necessary to accommodate an increased deployment of EVs within New York State by reducing the upfront costs of building charging stations for EVs. The Integrated Energy Data Resource (IEDR) establishes a statewide centralized computer platform that “will allow effective access to useful energy data and information from New York’s electric, gas, and steam utilities – and other sources – to support new and innovative clean energy business models that deliver benefits to New York energy customers.”  The “Electric EE/BE” program for home heating electrification using heat pumps and another for transmission upgrades needed to support the buildout of wind and solar developments.  This is the other large ($279 million) cost component.  The program categories descriptions that did not include costs total only $48 million.

The purpose of this post is to estimate the necessary cost recoveries for renewable energy development with the latest information.  Informational Report Table 8: Authorized Funding to Date “gives a sense” of some of the expenditures that will ultimately be recovered in rates. The Informational Report explains:

This annual report is a review of actual costs incurred by ratepayers to date in support of various programs and projects to implement the CLCPA and does not fully capture potential future expenditures, including estimated costs already authorized by the Commission but not yet recovered in rates. To complement this overview of cost recoveries incurred to date, we also present below a table of the various programs and the total amount of estimated costs associated with each authorized by the Commission to date. Table 8 gives a sense of expenditures that ratepayers could ultimately see recovered in rates. These values are conservative and reflect both past and prospective estimated costs.

The takeaway message from Table 8 is that the authorized funding to date of program costs that will eventually make their way to ratepayer bills totals $43.756 billion.  I assume that all the CES costs ($25.242 billion) are associated with renewable energy development.  Although there are other components that could support the zero-emissions mandates, I am not aware of proposed adjustments to any other programs.

Offshore Wind (OSW) Transmission Support

The purpose of this post is to update the data in Table 8 with the latest information on renewable energy development costs.  The first additional item is the necessary transmission upgrade for offshore wind.  Buried in a footnote is an admission that these are not all the costs authorized.  Footnote 7 in Table 8 states:

Not included in this table is the Propel NY transmission project, selected by the NYISO Board in June 2023 in response to the Commission’s declaration of a public policy transmission need (PPTN) to support injections of offshore wind energy to the Long Island system by 2030 at an estimated cost of $3.36 billion. Since the Commission did not directly approve this project, the estimated cost is not captured in the Table 8.

I posted an article about this component of the offshore wind implementation requirements earlier this year.  The Department of Public Service has an Order for Public Policy Transmission Need (PPTN) (Case 20-E-0497) regarding Climate Act requirements related to offshore wind that drive the need to expand the number of transmission facilities between Long Island and the rest of the State.  These transmission system upgrades are needed to get the generated offshore wind from where it comes on shore to where it is needed in the state.

In response to the New York Independent System Operator (NYISO) request for proposals for the PPTN 17 bids were received.   The average total cost estimate was $7.1 billion, the maximum was $16.9 billion and the minimum was $2.1 billion.  In June 2023, NYISO chose the Propel NY transmission project totaling $3.28 billion.

These are not the only additional costs needed to support offshore wind.  The Propel NY costs are only for a portion of the new transmission lines needed and do not include additional costs associated with the impacts on the existing transmission and distribution systems on Long Island.  This is the cost associated with 3,000 MW of offshore wind.  The Climate Act goal is for 9,000 MW and the Scoping Plan Integration Analysis projects that 12,675 MW of offshore wind will be needed by 2040 in the Strategic Use of Low-Carbon Fuels mitigation scenario. 

Offshore Wind Cost Renegotiation

The Informational Report Table 8 program costs include the costs for OSW wind projects that have contracts.  One reason for this post is that inflation and supply chain issues have led developers to ask that the contracts be renegotiated.  James Hanley writes:

Multiple offshore wind projects that are not even built yet have asked the state’s Public Service Commission (PSC) to renegotiate their strike prices—the amount they will be paid per megawatt hour (MWh) of electricity produced. (A megawatt hour is roughly enough electricity to power 750 homes for one hour.) 

One of the glaring deficiencies of the Hochul Administration’s Climate Act implementation is the lack of information about ratepayer impacts.  The Informational Report was the first report that provided any estimates of ratepayer impacts and that was a Climate Act mandate.  In order to get a feel for the ratepayer impacts of the contract renegotiations it is up to outside parties to provide estimates.  Multiple Intervenors and the Municipal Electric Utilities Association of New York State (“Customer Advocates”) recently submitted Supplemental Comments to the New York State Public Service Commission that includes estimates of the incremental costs to customers for these renegotiated contracts.

The Consumer Advocates comments addressed the NYSERDA submitted comments that estimated the change in contract strike prices that would result from contract modifications requested by offshore wind developers.  NYSERDA did not provide any estimate of the effect on consumer costs so Consumer Advocates made their own.  Their analysis found that the proposed changes could impose on customers incremental costs of between $20.8 billion and $37.6 billion.  In my original article I did not pick up on the fact that the incremental costs accrue over 30 years.  In other words I should have divided by 30 to get the annual ratepayer impact.

ACENY Tier 1 REC Adjustment

The crony capitalists representing other renewable developments lost no time in submitting their own petitions for additional money.  The Alliance for Clean Energy New York (ACENY) submitted their own petition in June 2023 that claimed:

A number of factors not seen in decades, including the COVID-19 pandemic and the war of aggression in Europe with Russia’s invasion of Ukraine, have collectively led to intractable supply chain bottlenecks and labor constraints. Meanwhile, unprecedented increases in demand for new renewable energy development relative to other goods and services as more States and countries implement their own climate change initiatives has further exacerbated these inflationary effects for the renewable energy industry, leading to wholly unpredictable upsurges in the costs of renewable energy development.

The end result: skyrocketing, unpredictable inflationary spikes. As established herein, these effects collectively (“Post-COVID Impacts”) have eroded the viability of Awarded Projects that have not already been cancelled, are not operational and are not yet nearing operation (“Under Development Projects”). Proceeding with the Tier 1 REC program on a status quo basis is, thus, no longer viable.

Using the same methodology used for the offshore wind renegotiation costs, the Consumer Advocates estimated that the ACENY petition would add another $10.69 billion to ratepayer costs.  This value needs to be divided by 30 to get the annual impact.

Transmission Project Adjustments

The ACENY petition did not over similar adjustments for the Clean Path New York (CPNY) and Champlain Hudson Express (CHPE) transmission line projects. 

CPNY submitted their own petition asking for a similar adjustment:

Clean Path New York LLC (“CPNY”) requested that the New York Public Service Commission (“Commission”) authorize the New York State Energy Research and Development Authority (“NYSERDA”) to adjust CPNY’s strike price to adjust CPNY’s strike price attributable to the generation portion of the Tier 4 Renewable Energy Certificate Purchase and Sale Agreement entered into between CPNY and NYSERDA (the “CPNY Contract”), solely by the amount of the adjustment provided in response to the petition (the “Tier 1 Petition”) filed by the Alliance for Clean Energy New York (“ACE-NY”) requesting that the Commission authorize NYSERDA to incorporate an express adjustment mechanism provision in its Clean Energy Standard Tier 1 contracts (“Adjustment Mechanism”) for projects awarded through NYSERDA’s 2021 Renewable Energy Certificate (“REC”) Solicitation (“Under Development Projects”).  As ACE-NY explained, this corrective action will produce RECs that are consistent with New York Public Service Law Section 65 and is required due to the unforeseen and severe market disruptions that have occurred since those solicitations were held. The changes have resulted in materially adverse impacts that have rendered the Under Development Projects economically infeasible.

CHPE also submitted a petition with Hydro Quebec Energy Services (HQES).  The introduction to the petition states:

Unprecedented economic factors including rising interest rates, inflation, and supply shortages are jeopardizing all clean energy infrastructure projects needed to achieve New York’s climate goals. With respect to the CHPE Project, the construction costs for its new-build transmission components have increased significantly from the time of the CHPE Project bid submission (in May 2021) to the closing on the financing for the U.S. portion of the CHPE Project in October 2022, shortly after which construction began. Notwithstanding these challenges, Petitioners’ actions allowed the CHPE Project to start construction, and they remain committed to this necessary project and to the HQUS REC Contract.

The CHPE Project is indisputably critical to maintaining reliability while achieving New York State’s longstanding goal of decarbonizing Downstate New York energy consumption. By entering service in Spring 2026 as anticipated, the CHPE Project will create sufficient “reliability margins within New York City” to push off the need to add new generating or other resources for up to five or six years.

Like the other many developers that have filed petitions, Petitioners faced global supply chain shortages and market disruption, and the substantial negative impacts of inflation and interest rate increases on construction costs in both the United States and Canada. For this reason, the CHPE Project is similarly situated to the other major New York renewable energy project petitioners seeking cost adjustments and should be treated equally and consistently with respect to any cost adjustments granted by the Commission.

Accordingly, Petitioners propose that the Commission authorize NYSERDA to adopt a program-wide cost adjustment formula covering all Approved Projects, based on the inflationary adjustment already provided by NYSERDA for new Tier 1 REC contracts.9 The adoption of a program-wide, formula-based price adjustment for construction costs for all new-build project components is Petitioners’ preference, as it would treat all developers equally.

Consumer Advocates did not calculate an impact to consumers for these two project renegotiations.  I did not try to estimate any additional ratepayer impacts for them.

Discussion

The Utility Intervention Unit, Division of Consumer Protection NYS Department of State submitted a petition responding to ACENY.  They describe the ACENY petition as follows:

The ACE-NY petition seeks a one-time adjustment mechanism for solar and wind projects claiming it would restore “viability to support project completion, while also ensuring efficiency, transparency, and simplicity in their application.” 

ACE-NY proposes an adjustment factor on each project so that Under Development Projects will become economically viable and claims this is necessary to meet a viable schedule to achieve the 2030 goal.

The Utility Intervention Unit had  issues with the ACENY petition:

Yet, PA Consulting’s assessment did not consider “specific circumstances faced by individual renewable energy project or developer.” Nor did they analyze which portion of Under Development Projects would be successful, fail, or offer new projects in subsequent solicitations due to the number of judgement calls that would be required.10 While PA Consulting focused on the financial aspects, it did not consider or speak to whether the sought adjustment mechanism could overcome supply chain or labor shortages among the increase demand of renewable resources. Therefore, it appears ACE-NY and PA Consulting are proposing an adjustment factor with no guarantee that the 2030 goal will be met. Without such guarantees, UIU opposes the petition as requested and suggests the focus be on supporting only those projects worthy of ratepayers’ support.

For markets and competition to function efficiently, contracts and obligations should be honored. Altering contracts after terms are defined can diminish the competitive process that potentially disadvantages those bidders not selected in a respective solicitation and consumers who are paying for the project. The unsuccessful bidders may have included a risk premium that could be less than the REC price adjustment ACE-NY is seeking in its petition.

I agree with UIU.  There are implications not only to costs but also to the schedule for all the factors cited by the developers. 

Consolidated Ratepayer Cost Estimate

The following table lists all authorized and incremental relief ratepayer costs that could be on the backs of New York ratepayers except for the CPNY and CHPE project costs.  The Informational Report listed $43.8 billion in costs that have been authorized but are not yet in ratepayer bills.  That report did not include the $3.3 billion Propel NY transmission project needed for offshore wind.  If total costs for the Integration Analysis offshore wind projection are proportional to the offshore wind capacity (12,765 MW to 3,000 MW) the transmission upgrades for offshore wind will be $13.9 billion. The Consumer Advocate petition estimated ratepayer costs for the NYSERDA and ACENY petitions ranging from $26.4 billion to $48.4 billion.  When the Informational Report authorized funding to date, offshore wind transmission support, and the Consumer Advocate additional funding requirements are totaled the range is $73.47 billion to $105.7 billion.

Ratepayer Potential Impacts

The Informational Report included Table 7: 2022 Typical Monthly Electric Bills with Climate Act related costs disaggregated that was the first admission by the Hochul Administration of potential costs of the Climate Act to ratepayers.  The basis for the typical electric delivery and supply bills for 2022 was provided for the following customer types:

A.           Residential customers (600 kWh per month),

B.           Non-residential customers (50 kW & 12,600 kWh per month),

C.           Non-residential customers (2,000 kW & 720,000 kWh per month), and

D.           Non-residential high load factor customers (2,000 kW & 1,296,000 kWh per month).

PSC Staff requested that utilities disaggregate the cost components reported in Table 2 (electric) to determine CLCPA related impacts on customers as shown in Table 7.  Climate Act costs added between 9.8% and 3.7% to residential monthly electric bills in 2022.

This is the point where my mistake caused the results to go off the rails.  It turns out that I made the same mistake in a previous post too.  I pro-rated the Informational Report ratepayer Climate Act cost recoveries for $43.8 billion in costs for contracts that have been awarded but not yet authorized for cost recovery but did not account for a 30-year accrual.  In the original post I showed calculations two ways but will only show the slightly more refined version here. 

Recall that Table 4: 2022 Electric CLCPA Recoveries in the Informational Report summarizes costs recovered in 2022 by utilities for electric programs.  The table states that $1,176 million in Climate Act costs were recovered in 2022 and it shows the amount these costs affected utility bills for seven utilities and eight program categories.  I assume that future ratepayer costs will increase proportionally to the

Informational Report authorized funding to date, offshore wind transmission support, and the Consumer Advocate additional funding requirements in the range of $73.47 billion to $105.7 billion if these numbers are divided by 30 to account for the appropriate accrual rate.

Instead of using the ratio of the totals I prorated costs from the Table 8 program cost categories for all the additional costs expected and then scaled costs per utility for the lower and upper bounds. This adds another 4 to 20% increase in the Climate Act costs.  Ultimately, the PSC should provide the refined numbers not the Consumer Advocates or folks like me.  New Yorkers deserve the best estimates of ratepayer costs.

Note that if you want the spreadsheet with these data please contact me.

Conclusion

I believe that the Hochul Administration is trying hard to coverup the ratepayer cost impacts.  The Informational Report is a useful first estimate of ratepayer impacts but it was a required Climate Act mandate.  It provides as little information as possible.  For example, it excludes the Propel NY transmission costs because “the Commission did not directly approve this project.”  The intent of the Climate Act mandate was to describe all the effects of the Act on ratepayers not just what is politically palatable.   

The costs shown here are notable and they are not the total costs.   All the ratepayer costs that are described in this post are only for the supply portion of utility bills.  The Hochul Administration is implementing a Cap-and-Invest program that will increase the costs of delivery.  There has been absolutely no hint of the expected costs for the cap-and-invest program but it will certainly cause an additional increase in costs.  In addition, this is just for the costs of the electricity.  The Climate Act plan is to convert homes and transportation to zero emissions energy too so New Yorkers will have to pick up those costs too.

When I thought that the Climate Act would more than double electric utility bills I said I expected that a ratepayer revolt would occur when the public caught on.  Even at these lower costs I believe that the Hochul Administration has a vested interest in covering up these costs up for as long as possible.  I am disappointed that there have not been news stories about this issue.  There always seems to be space for the latest unsubstantiated claim that an unusual weather event is proof of climate change but there does not appear to be room to show that New York’s plan to do something about climate change will make electricity unaffordable for many. The real impacts of energy poverty on health and welfare should be a higher priority than the speculative effects of climate change that New York cannot alter because New York GHG emissions are less than one half of one percent of global emissions and global emissions have been increasing on average by more than one half of one percent per year since 1990.  Anything we do is supplanted by emission increases elsewhere in less than a year.

Electric Ratepayer Bills Must Explode to Meet Climate Act Mandates

Update: There is an error in this post.  Please refer to the corrected version .   Dr. Jonathan Lesser pointed out that I need to adjust the consolidated costs described here for contracts that have been awarded but not yet authorized for cost recovery and other requested costs but did not account for a 30-year accrual.  As a result the correct increases are much lower,  but I still think that these costs are extraordinary albeit not explosive as I said here.

This post consolidates all the recent information on added costs associated with renewable energy development needed to meet Climate Leadership & Community Protection Act (Climate Act) targets that have been authorized or requested.  These costs will eventually show up in electric bills and the projected cost increases are extraordinary.

I have been following the Climate Act since it was first proposed, submitted comments on the Climate Act implementation plan, and have written over 350 articles about New York’s net-zero transition.  I have devoted a lot of time to the Climate Act because I believe the ambitions for a zero-emissions economy embodied in the Climate Act outstrip available renewable technology such that the net-zero transition will do more harm than good.  The opinions expressed in this post do not reflect the position of any of my previous employers or any other company I have been associated with, these comments are mine alone.

Climate Act Background

The Climate Act established a New York “Net Zero” target (85% reduction and 15% offset of emissions) by 2050.  It includes an interim 2030 reduction target of a 40% reduction by 2030 and a requirement that all electricity generated be “zero-emissions” by 2040. The Climate Action Council is responsible for preparing the Scoping Plan that outlines how to “achieve the State’s bold clean energy and climate agenda.”  In brief, that plan is to electrify everything possible using zero-emissions electricity. The Integration Analysis prepared by the New York State Energy Research and Development Authority (NYSERDA) and its consultants quantifies the impact of the electrification strategies.  That material was used to develop the Draft Scoping Plan.  After a year-long review, the Scoping Plan recommendations were finalized at the end of 2022.  In 2023 the Scoping Plan recommendations are supposed to be implemented through regulation and legislation. 

Renewable Procurement Background

The NYSERDA is primarily responsible for facilitating projects to meet  Governor Hochul’s target of generating 70 percent of New York State’s electricity from renewable sources by 2030.  For background, I tried to figure out those projects will be funded.  One component is solicitations for large-scale renewables.  That includes a two-step process consisting of:

  1. Step One Eligibility Application: A qualifying step through which the proposer must provide evidence that the Bid Facility is Tier 1 eligible and other general information about the Proposer and the Bid Facility. All Step One Eligibility Applications must be submitted via the RESRFP22-1 solicitation website
  2. Step Two Bid Proposal: A competitive Bid Proposal step, through which NYSERDA will:

a. examine Bid Proposals to determine whether they demonstrate that the Bid Facility and Proposer meet the Minimum Threshold Requirements; and

b. for Bid Proposals that meet those Minimum Threshold Requirements, perform a competitive evaluation based on price and non-price factors.

The focus of this post is on ratepayer costs associated with the zero-emissions mandates.  I did some research on the funding mechanisms and this is how I think renewable energy projects are funded.  The Clean Energy Standard (CES) is the primary method used to “turn New York State’s ambitious clean energy goal into a reality.”  The CES has two mechanisms: the renewable energy standard (RES) and the zero-emissions credit (ZEC) requirement designed to help create a low carbon energy system.  According to NYSERDA:

  • The RES requires every load serving entity (LSE)
     in New York State to procure renewable energy certificates(RECs)
     associated with new renewable energy resources—known as Tier 1—for their retail customers. If LSEs cannot demonstrate they are meeting the Tier 1 obligation through the possession of RECs, they may make alternative compliance payments (ACPs).
  • The ZEC requirement mandates the LSEs procure ZECs from NYSERDA. The number of ZECs is based on each LSE’s proportionate amount of statewide load, or energy demanded, in a given compliance year.

In addition to these programs, NYSERDA is also advancing offshore wind energy projects through its Offshore Wind Program. NYSERDA also works with its State partners and local communities to rapidly advance new “Build-Ready” projects, prioritizing the development of existing or abandoned commercial sites, brownfields, landfills, former industrial sites, and other abandoned or underutilized sites.

According to NYSERDA:

The Renewable Energy Standard (RES) is a mechanism enacted by the Clean Energy Standard to help New York State reach its ambitious clean energy goals and transition toward a low carbon energy system. The RES requires utilities and other load serving entities in the State to procure Tier 1 renewable energy credits (RECs).

The LSEs must pay for the RECs.  NYSERDA obtains the RECs from developers in auctions.  For example, the 2022 solicitation tried to “procure approximately 4.5 million Tier 1 eligible Renewable Energy Certificates (RECs) from eligible facilities that enter commercial operation on or after January 1, 2015 and on or before May 31, 2025, unless extended to May 31, 2028.”

The costs for the RECs are passed on to consumers in several steps.  First, NYSERDA awards contracts for the RECs to specific projects.  There is no guarantee that a project that has been awarded a contract will actually get built and operate.  The Utility Intervention Unit (UIU), Division of Consumer Protection NYS Department of State recently submitted a petition that noted that “only a tiny subset of awarded projects has completed the entire solicitation cycle and reached operational status (“Operational Projects”)”.   When a project starts to operate, they are awarded RECs which are sold to the LSEs.  The LSEs pass those costs on to their customers only after the PSC authorizes the cost in a utility rate case.

Note, however, that there are other programs described in this article that are also needed to meet the zero-emissions mandate that also add to consumer utility bills.

Informational Report on Ratepayer Costs

The Department of Public Service (DPS) first annual informational report (“Informational Report”) on the implementation of the Climate Act was released in July.  The report is notable because it provided the first Climate Act ratepayer cost estimates provided by the Hochul Administration.  However, those estimates only cover projects that are in the utility rate cases in 2022.   There are many more costs that will eventually show up in electric bills.

The report was based on data submitted by utilities that were collected to pay for Climate Act projects.  The Department of Public Service presentation on the Informational Report noted that “ the estimates of total funding authorized by the Commission to date for various clean energy programs in some instances reflect actions that pre-date the enactment of the Climate Act.”  The conclusion states that the information presented “represents  direct effects of Climate Act implementation only, and only the portion of direct effects of programs over which the Commission has oversight authority.” 

In an earlier post I described Table 4: 2022 Electric CLCPA Recoveries from the report that summarizes costs recovered in 2022 by utilities for electric programs.  The table states that $1,176 million in Climate Act costs were recovered in 2022 and it shows the amount these costs affected utility bills for seven utilities and eight program categories.  I doubt that there are many people who understand what is in each of these different programs but for the purpose of trying to estimate ratepayer costs for renewable energy development we need to summarize the programs.  The CES awards discussed above accounted for $348 million of that total.  The Clean Energy Fund (CEF) “was established as a commitment to clean energy and efficiency measures”.  The latest annual performance report lists four CEF components totaling $500 million: market development, innovation & research, NY-Sun (the distributed solar program), and the NY Green Bank.  The value of distributed energy resources (VDER) also known as the Value Stack is a new mechanism to compensate energy created by distributed energy resources, like residential solar.  The EV Make Ready Program goal is to support the development of electric infrastructure and equipment necessary to accommodate an increased deployment of EVs within New York State by reducing the upfront costs of building charging stations for EVs. The Integrated Energy Data Resource (IEDR) establishes a statewide centralized computer platform that “will allow effective access to useful energy data and information from New York’s electric, gas, and steam utilities – and other sources – to support new and innovative clean energy business models that deliver benefits to New York energy customers.”  The “Electric EE/BE” program for home heating electrification using heat pumps and another for transmission upgrades needed to support the buildout of wind and solar developments.  This is the other large ($279 million) cost component.  The program categories descriptions that did not include costs total only $48 million.

The purpose of this post is to estimate the necessary cost recoveries for renewable energy development with the latest information.  Informational Report Table 8: Authorized Funding to Date “gives a sense” of some of the expenditures that will ultimately be recovered in rates. The Informational Report explains:

This annual report is a review of actual costs incurred by ratepayers to date in support of various programs and projects to implement the CLCPA and does not fully capture potential future expenditures, including estimated costs already authorized by the Commission but not yet recovered in rates. To complement this overview of cost recoveries incurred to date, we also present below a table of the various programs and the total amount of estimated costs associated with each authorized by the Commission to date. Table 8 gives a sense of expenditures that ratepayers could ultimately see recovered in rates. These values are conservative and reflect both past and prospective estimated costs.

The takeaway message from Table 8 is that the authorized funding to date of program costs that will eventually make their way to ratepayer bills totals $43.756 billion.  I assume that all the CES costs ($25.242 billion) are associated with renewable energy development.  Although there are other components that could support the zero-emissions mandates, I am not aware of proposed adjustments to any other programs.

Offshore Wind (OSW) Transmission Support

The purpose of this post is to update the data in Table 8 with the latest information on renewable energy development costs.  The first additional item is the necessary transmission upgrade for offshore wind.  Buried in a footnote is an admission that these are not all the costs authorized.  Footnote 7 in Table 8 states:

Not included in this table is the Propel NY transmission project, selected by the NYISO Board in June 2023 in response to the Commission’s declaration of a public policy transmission need (PPTN) to support injections of offshore wind energy to the Long Island system by 2030 at an estimated cost of $3.36 billion. Since the Commission did not directly approve this project, the estimated cost is not captured in the Table 8.

I posted an article about this component of the offshore wind implementation requirements earlier this year.  The Department of Public Service has an Order for Public Policy Transmission Need (PPTN) (Case 20-E-0497) regarding Climate Act requirements related to offshore wind that drive the need to expand the number of transmission facilities between Long Island and the rest of the State.  These transmission system upgrades are needed to get the generated offshore wind from where it comes on shore to where it is needed in the state.

In response to the New York Independent System Operator (NYISO) request for proposals for the PPTN 17 bids were received.   The average total cost estimate was $7.1 billion, the maximum was $16.9 billion and the minimum was $2.1 billion.  In June 2023, NYISO chose the Propel NY transmission project totaling $3.28 billion.

These are not the only additional costs needed to support offshore wind.  The Propel NY costs are only for a portion of the new transmission lines needed and do not include additional costs associated with the impacts on the existing transmission and distribution systems on Long Island.  This is the cost associated with 3,000 MW of offshore wind.  The Climate Act goal is for 9,000 MW and the Scoping Plan Integration Analysis projects that 12,675 MW of offshore wind will be needed by 2040 in the Strategic Use of Low-Carbon Fuels mitigation scenario. 

Offshore Wind Cost Renegotiation

The Informational Report Table 8 program costs include the costs for OSW wind projects that have contracts.  One reason for this post is that inflation and supply chain issues have led developers to ask that the contracts be renegotiated.  James Hanley writes:

Multiple offshore wind projects that are not even built yet have asked the state’s Public Service Commission (PSC) to renegotiate their strike prices—the amount they will be paid per megawatt hour (MWh) of electricity produced. (A megawatt hour is roughly enough electricity to power 750 homes for one hour.) 

One of the glaring deficiencies of the Hochul Administration’s Climate Act implementation is the lack of information about ratepayer impacts.  The Informational Report was the first report that provided any estimates of ratepayer impacts and that was a Climate Act mandate.  In order to get a feel for the ratepayer impacts of the contract renegotiations it is up to outside parties to provide estimates.  Multiple Intervenors and the Municipal Electric Utilities Association of New York State (“Customer Advocates”) recently submitted Supplemental Comments to the New York State Public Service Commission that includes estimates of the incremental costs to customers for these renegotiated contracts.

The Consumer Advocates comments addressed the NYSERDA submitted comments that estimated the change in contract strike prices that would result from contract modifications requested by offshore wind developers.  NYSERDA did not provide any estimate of the effect on consumer costs so Consumer Advocates made their own.  Their analysis found that the proposed changes could impose on customers incremental costs of between $20.8 billion and $37.6 billion.

ACENY Tier 1 REC Adjustment

The crony capitalists representing other renewable developments lost no time in submitting their own petitions for additional money.  The Alliance for Clean Energy New York (ACENY) submitted their own petition in June 2023 that claimed:

A number of factors not seen in decades, including the COVID-19 pandemic and the war of aggression in Europe with Russia’s invasion of Ukraine, have collectively led to intractable supply chain bottlenecks and labor constraints. Meanwhile, unprecedented increases in demand for new renewable energy development relative to other goods and services as more States and countries implement their own climate change initiatives has further exacerbated these inflationary effects for the renewable energy industry, leading to wholly unpredictable upsurges in the costs of renewable energy development.

The end result: skyrocketing, unpredictable inflationary spikes. As established herein, these effects collectively (“Post-COVID Impacts”) have eroded the viability of Awarded Projects that have not already been cancelled, are not operational and are not yet nearing operation (“Under Development Projects”). Proceeding with the Tier 1 REC program on a status quo basis is, thus, no longer viable.

Using the same methodology used for the offshore wind renegotiation costs, the Consumer Advocates estimated that the ACENY petition would add another $10.69 billion to ratepayer costs.

Transmission Project Adjustments

The ACENY petition did not over similar adjustments for the Clean Path New York (CPNY) and Champlain Hudson Express (CHPE) transmission line projects. 

CPNY submitted their own petition asking for a similar adjustment:

Clean Path New York LLC (“CPNY”) requested that the New York Public Service Commission (“Commission”) authorize the New York State Energy Research and Development Authority (“NYSERDA”) to adjust CPNY’s strike price to adjust CPNY’s strike price attributable to the generation portion of the Tier 4 Renewable Energy Certificate Purchase and Sale Agreement entered into between CPNY and NYSERDA (the “CPNY Contract”), solely by the amount of the adjustment provided in response to the petition (the “Tier 1 Petition”) filed by the Alliance for Clean Energy New York (“ACE-NY”) requesting that the Commission authorize NYSERDA to incorporate an express adjustment mechanism provision in its Clean Energy Standard Tier 1 contracts (“Adjustment Mechanism”) for projects awarded through NYSERDA’s 2021 Renewable Energy Certificate (“REC”) Solicitation (“Under Development Projects”).  As ACE-NY explained, this corrective action will produce RECs that are consistent with New York Public Service Law Section 65 and is required due to the unforeseen and severe market disruptions that have occurred since those solicitations were held. The changes have resulted in materially adverse impacts that have rendered the Under Development Projects economically infeasible.

CHPE also submitted a petition with Hydro Quebec Energy Services (HQES).  The introduction to the petition states:

Unprecedented economic factors including rising interest rates, inflation, and supply shortages are jeopardizing all clean energy infrastructure projects needed to achieve New York’s climate goals. With respect to the CHPE Project, the construction costs for its new-build transmission components have increased significantly from the time of the CHPE Project bid submission (in May 2021) to the closing on the financing for the U.S. portion of the CHPE Project in October 2022, shortly after which construction began. Notwithstanding these challenges, Petitioners’ actions allowed the CHPE Project to start construction, and they remain committed to this necessary project and to the HQUS REC Contract.

The CHPE Project is indisputably critical to maintaining reliability while achieving New York State’s longstanding goal of decarbonizing Downstate New York energy consumption. By entering service in Spring 2026 as anticipated, the CHPE Project will create sufficient “reliability margins within New York City” to push off the need to add new generating or other resources for up to five or six years.

Like the other many developers that have filed petitions, Petitioners faced global supply chain shortages and market disruption, and the substantial negative impacts of inflation and interest rate increases on construction costs in both the United States and Canada. For this reason, the CHPE Project is similarly situated to the other major New York renewable energy project petitioners seeking cost adjustments and should be treated equally and consistently with respect to any cost adjustments granted by the Commission.

Accordingly, Petitioners propose that the Commission authorize NYSERDA to adopt a program-wide cost adjustment formula covering all Approved Projects, based on the inflationary adjustment already provided by NYSERDA for new Tier 1 REC contracts.9 The adoption of a program-wide, formula-based price adjustment for construction costs for all new-build project components is Petitioners’ preference, as it would treat all developers equally.

Consumer Advocates did not calculate an impact to consumers for these two project renegotiations.  I did not try to estimate any additional ratepayer impacts for them.

Discussion

The Utility Intervention Unit, Division of Consumer Protection NYS Department of State submitted a petition responding to ACENY.  They describe the ACENY petition as follows:

The ACE-NY petition seeks a one-time adjustment mechanism for solar and wind projects claiming it would restore “viability to support project completion, while also ensuring efficiency, transparency, and simplicity in their application.” 

ACE-NY proposes an adjustment factor on each project so that Under Development Projects will become economically viable and claims this is necessary to meet a viable schedule to achieve the 2030 goal.

The Utility Intervention Unit had  issues with the ACENY petition:

Yet, PA Consulting’s assessment did not consider “specific circumstances faced by individual renewable energy project or developer.” Nor did they analyze which portion of Under Development Projects would be successful, fail, or offer new projects in subsequent solicitations due to the number of judgement calls that would be required.10 While PA Consulting focused on the financial aspects, it did not consider or speak to whether the sought adjustment mechanism could overcome supply chain or labor shortages among the increase demand of renewable resources. Therefore, it appears ACE-NY and PA Consulting are proposing an adjustment factor with no guarantee that the 2030 goal will be met. Without such guarantees, UIU opposes the petition as requested and suggests the focus be on supporting only those projects worthy of ratepayers’ support.

For markets and competition to function efficiently, contracts and obligations should be honored. Altering contracts after terms are defined can diminish the competitive process that potentially disadvantages those bidders not selected in a respective solicitation and consumers who are paying for the project. The unsuccessful bidders may have included a risk premium that could be less than the REC price adjustment ACE-NY is seeking in its petition.

I agree with UIU.  There are implications not only to costs but also to the schedule for all the factors cited by the developers. 

Consolidated Ratepayer Cost Estimate

The following table lists all authorized and incremental relief ratepayer costs that could be on the backs of New York ratepayers except for the CPNY and CHPE project costs.  The Informational Report listed $43.8 billion in costs that have been authorized but are not yet in ratepayer bills.  That report did not include the $3.3 billion Propel NY transmission project needed for offshore wind.  If total costs for the Integration Analysis offshore wind projection are proportional to the offshore wind capacity (12,765 MW to 3,000 MW) the transmission upgrades for offshore wind will be $13.9 billion. The Consumer Advocate petition estimated ratepayer costs for the NYSERDA and ACENY petitions ranging from $26.4 billion to $48.4 billion.  When the Informational Report authorized funding to date, offshore wind transmission support, and the Consumer Advocate additional funding requirements are totaled the range is $73.47 billion to $105.7 billion.

Ratepayer Potential Impacts

The Informational Report included Table 7: 2022 Typical Monthly Electric Bills with Climate Act related costs disaggregated that was the first admission by the Hochul Administration of potential costs of the Climate Act to ratepayers.  The basis for the typical electric delivery and supply bills for 2022 was provided for the following customer types:

A.           Residential customers (600 kWh per month),

B.           Non-residential customers (50 kW & 12,600 kWh per month),

C.           Non-residential customers (2,000 kW & 720,000 kWh per month), and

D.           Non-residential high load factor customers (2,000 kW & 1,296,000 kWh per month).

PSC Staff requested that utilities disaggregate the cost components reported in Table 2 (electric) to determine CLCPA related impacts on customers as shown in Table 7.  Climate Act costs added between 9.8% and 3.7% to residential monthly electric bills in 2022.

In a previous post I pro-rated the Informational Report ratepayer Climate Act cost recoveries for the $43.8 billion in costs for contracts that have been awarded but not yet authorized for cost recovery.  I simply calculated the ratio of the authorized Climate Act funding to date ($43.8 billion) to the Climate Act costs that have been authorized and were in the 2022 residential bills ($1.2 billion).   For a rough approximation of impacts by utility I simply multiplied the ratio by each of the monthly Climate Act disaggregated cost components reported by the utilities to determine CLCPA future related impacts on customers. This will not give an exact utility-specific estimate because the money authorizations per utility for 2022 and the future will not necessarily be the same.  The following table uses the same methodology for all the expected ratepayer costs. 

These numbers are so large that I suspect that I am missing something.  I tried an alternative way to estimate ratepayer impacts.  In the alternative approach I prorated costs from the Table 8 program cost categories for all the additional costs expected and then scaled costs per utility for the lower and upper bounds.  This probably is a better estimate of utility costs but the numbers are still extraordinarily high.

I believe that when all the costs not included in the Informational Report are authorized for rate cases that residential bills will more than double, at least.  Ultimately, the PSC should provide the refined numbers not the Consumer Advocates or folks like me.  New Yorkers deserve the best estimates.

Conclusion

I believe that the Hochul Administration is trying hard to coverup the ratepayer cost impacts.  The Informational Report is a useful first estimate of ratepayer impacts but it was a required Climate Act mandate.  It provides as little information as possible.  For example, it excludes the Propel NY transmission costs because “the Commission did not directly approve this project.”  The intent of the Climate Act mandate was to describe all the effects of the Act on ratepayers not just what is politically palatable.   

Furthermore, even the additional costs that I provided in this post are not the total costs.   All the ratepayer costs that are described in this post are only for the supply portion of utility bills.  The Hochul Administration is implementing a Cap-and-Invest program that will increase the costs of delivery.  There has been absolutely no hint of the expected costs for this program but it will certainly cause an additional increase in costs.  In addition, this is just for the costs of the electricity.  The Climate Act plan is to convert homes and transportation to zero emissions energy too so New Yorkers will have to pick up those costs too.

I concluded that electric utility bills would double but I believe that is a lowball estimate.  I think that most ratepayers would be grabbing pitchforks and torches to march on Albany in protest of  these projected utility bill increases if they knew what was coming their way.  Clearly the Hochul Administration has a vested interest in covering up these costs up for as long as possible.  I am disappointed that there have not been news stories about this issue.  There always seems to be space for the latest unsubstantiated claim that an unusual weather event is proof of climate change but there does not appear to be room to show that New York’s plan to do something about it will make electricity unaffordable for many. The real impacts of energy poverty on health and welfare should be a higher priority than the speculative effects of climate change that New York cannot affect because New York GHG emissions are less than one half of one percent of global emissions and global emissions have been increasing on average by more than one half of one percent per year since 1990.  Anything we do is supplanted by emission increases elsewhere.

Climate Act Offshore Wind Costs

Update (9/17/23): I corrected an error in this post.  Dr. Jonathan Lesser pointed out that I need to adjust the offshore wind costs described here to account for a 30-year accrual. 

One of the important renewable energy components of the net-zero transition in New York’s Climate Leadership & Community Protection Act (Climate Act) is offshore wind. I recently did an update on several offshore wind issues that included a description of an offshore wind cost analysis.  This is a follow up to that discussion with an emphasis on New York offshore wind costs.  The Hochul Administration is doing everything possible to hide the costs of the Climate Act but the immense costs of offshore wind are getting too large to hide.

I have been following the Climate Act since it was first proposed, submitted comments on the Climate Act implementation plan, and have written over 350 articles about New York’s net-zero transition.  I have devoted a lot of time to the Climate Act because I believe the ambitions for a zero-emissions economy embodied in the Climate Act outstrip available renewable technology such that the net-zero transition will do more harm than good.  The opinions expressed in this post do not reflect the position of any of my previous employers or any other company I have been associated with, these comments are mine alone.

Climate Act Background

The Climate Act established a New York “Net Zero” target (85% reduction and 15% offset of emissions) by 2050.  It includes an interim 2030 reduction target of a 40% reduction by 2030 and a requirement that all electricity generated be “zero-emissions” by 2040. The Climate Action Council is responsible for preparing the Scoping Plan that outlines how to “achieve the State’s bold clean energy and climate agenda.”  In brief, that plan is to electrify everything possible using zero-emissions electricity. The Integration Analysis prepared by the New York State Energy Research and Development Authority (NYSERDA) and its consultants quantifies the impact of the electrification strategies.  That material was used to develop the Draft Scoping Plan.  After a year-long review, the Scoping Plan recommendations were finalized at the end of 2022.  In 2023 the Scoping Plan recommendations are supposed to be implemented through regulation and legislation. 

Off Shore Wind (OSW) is supposed to be a major renewable resource in the net-zero electric energy system.  The Climate Act mandates 9,000 MW of Off Shore Wind (OSW) generating capacity by 2035.  The Integration Analysis modeling used to develop the Scoping Plan projects OSW capacity at 6,200 MW by 2030, 9,096 MW by 2035 and reaches 14,364 MW in 2040.  On the other hand, the New York Independent System Operator 2021-2040 System & Resource Outlook expects 5,036 MW in 2030 and 9,000 MW in 2035 with no additional development after that.  By 2030 the Integration Analysis predicts that 14% of the electric energy (GWh) produced will come from OSW and the Resource Outlook predicts nearly as much (12%).  This is an extraordinary build-out for a resource that is currently non-existent.  There are significant differences in the buildout projections that deserve to be reconciled.

OSW Transmission Support

In order to determine the total cost to New Yorkers for OSW it is necessary to consider the transmission upgrade costs.  I posted an article about this component of the OSW implementation requirements earlier this year.  The Department of Public Service has an Order for Public Policy Transmission Need (PPTN) (Case 20-E-0497) regarding Climate Act requirements related to offshore wind that drive the need to expand the number of transmission facilities between Long Island and the rest of the State.  These transmission system upgrades are needed to get the generated offshore wind from where it comes on shore to where it is needed in the state.

The draft NYISO Long Island Public Policy Transmission Need (PPTN) report predicts that the transmission upgrades will provide savings to the system:

The Long Island PPTN project simulations all show improvements in the export capability of Long Island by adding tie lines between Long Island and the lower Hudson Valley. This added transfer capacity and upgrades to the internal Long Island system reduce the amount of curtailment from offshore wind resources. The energy produced through reduced curtailment of offshore wind resources can then be used to offset more expensive generation to meet New York’s energy demand and, therefore, produce a production cost savings. Production cost savings are also created by offsetting high-cost energy imports from neighboring regions with lower cost New York-based generation that was previously inaccessible due to transmission congestion.

In general, all of the proposed projects produce savings by unbottling offshore wind resources in Long Island and reducing the amount of imports from neighboring regions. The figure below shows the estimated production cost savings for each project over a 20-year period in 2022 real million dollars.

The New York Independent System Operator (NYISO) Electric System Planning Working Group  (March 24, 2023 and April 3, 2023) evaluated independent cost estimates developed by NYISO’s consultant for proposed projects to address this issue.  In response to the NYISO’s request for proposals for the PPTN 17 bids were received.   The average total cost estimate was $7.1 billion, the maximum was $16.9 billion and the minimum was $2.1 billion.  In June 2023, NYISO chose the Propel NY transmission project totaling $3.28 billion.

The transmission upgrades are one of the hidden costs of OSW.  Without this connection upgrade as much as 92% of 3000 MW of off-shore wind which costs $15 billion would not be deliverable.  However, it comes at an annual average subsidy of $339 million.  Unfortunately, the indirect subsidy costs described are not the only costs.  These costs are only for the new transmission and do not include additional costs associated with the impacts on the existing transmission and distribution systems on Long Island.  In addition, this is the cost associated with 3,000 MW of offshore wind.  The Climate Act goal is for 9,000 MW and the Scoping Plan Integration Analysis projects that 12,675 MW of offshore wind will be needed by 2040 in the Strategic Use of Low-Carbon Fuels mitigation scenario.  If the transmission costs are proportional that would mean that this indirect subsidy alone would be at least $1,356 million a year for the Integration Analysis.

Offshore Wind Cost Renegotiation

The primary reason for this post is that inflation and supply chain issues have led developers to ask that the contracts be renegotiated.  James Hanley writes:

Multiple offshore wind projects that are not even built yet have asked the state’s Public Service Commission (PSC) to renegotiate their strike prices—the amount they will be paid per megawatt hour (MWh) of electricity produced. (A megawatt hour is roughly enough electricity to power 750 homes for one hour.) 

One of the glaring deficiencies of the Hochul Administration’s Climate Act implementation is the lack of information about ratepayer impacts.  The Informational Report was the first report that provided any estimates of ratepayer impacts and that was a Climate Act mandate.  The report provides as little information as possible.  In order to get a feel for the ratepayer impacts of the contract renegotiations it is up to outside parties to provide estimates.  Multiple Intervenors and the Municipal Electric Utilities Association of New York State2 (“Customer Advocates”) recently submitted Supplemental Comments to the New York State Public Service Commission that includes estimates of the incremental costs to customers for these renegotiated contracts.

The Consumer Advocates comments addressed the NYSERDA submitted comments that estimated the change in contract strike prices that would result from contract modifications requested by offshore wind developers.  NYSERDA did not provide any estimate of the effect on consumer costs so Consumer Advocates made their own.  Their analysis found that the proposed changes could impose on customers incremental costs of at least $20.8 billion, and as much as $37.6 billion.

Discussion

In an earlier post I described the  first annual informational report (“Informational Report”) on the implementation of the Climate Act. It summarizes costs recovered in 2022 by utilities for electric programs and estimates that $1,175,788,000 in Climate Act costs were recovered in 2022 and it shows the amount these costs affected utility bills for seven utilities.  Table 7: “2022 Typical Monthly Electric Bills with Climate Act related costs” from that report shows that residential ratepayer utility bills already are higher by between 9.8% and 3.7% for the 2022 recovered costs.

 The following table lists the additional offshore wind authorized and incremental relief ratepayer costs that could be on the backs of New York ratepayers.  The Informational Report did not include the $3.3 billion Propel NY transmission project needed for offshore wind.  The Consumer Advocate petition estimated ratepayer costs for the NYSERDA petitions totaling $37.7 billion.  When all these costs are totaled ratepayers could be on the hook for an additional $41.0 billion for offshore wind.

In a previous post I extrapolated the Informational Report ratepayer Climate Act cost recoveries for $43.8 billion in costs for contracts that have been awarded but not yet authorized for cost recovery.  I simply calculated the ratio of the authorized Climate Act funding to date ($43.8 billion) to the Climate Act costs that have been authorized and were in the 2022 residential bills ($1.2 billion).   I did not account the fact that those costs are not applied to consumer bills in one year but in this analysis, I have assumed a 30-year accrual.  For a rough approximation of impacts by utility I simply multiplied the ratio by each of the monthly Climate Act disaggregated cost components reported by the utilities to determine CLCPA future related impacts on customers. This will not give an exact utility-specific estimate because the money authorizations per utility for 2022 and the future will not necessarily be the same.  The following table uses the same methodology for all the expected ratepayer costs due to these offshore wind projects.  I expect that the supply portion of every electric utility bill will more than double.

In response to similar extraordinary costs the British Government the recent Contracts for Difference (CfD) auction subsidies for renewable electricity generation were specified. Paul Homewood writes:

Participants in the auction bid for guaranteed prices, below a cap set by ministers in advance of the auction. The cap for offshore wind was set at £44/MWh (in 2012 prices, equivalent to around £70/MWh today). This is higher than successful bids in the past, yet no wind farm developers felt able to bid at this price. Wind industry claims that this is due to rising prices are implausible – CfD contracts are index-linked.


While offshore wind’s failure to bid may be surprising to some, perhaps even to the Government, it will come as no shock to those familiar with the long-term capital and operating cost trends for wind power, as revealed in audited financial statements. Costs have not been falling dramatically as the industry claimed. All around the world the wind industry is in trouble for the same reasons; costs remain high, and high levels of subsidy are needed to reward investors.

If New York were to revise its contracts to hold down costs I expect that the results would be the same.  That is to say, no one would bid because the industry is in deep financial trouble.

Conclusion

In conclusion it is important to note that all the ratepayer costs that are described in this post are only for the supply portion of utility bills.  The Hochul Administration is implementing a Cap-and-Invest program that will increase the costs of delivery.  There has been absolutely no hint of the expected costs for this program but it will certainly cause an increase.  Furthermore, this is just for the costs of the electricity.  The plan is to convert homes and transportation too.

Offshore wind is a key part of the planned Climate Act net-zero transition.  The New York Post notes that “In a fresh sign that New York’s state climate agenda is pure fantasy, contractors key to making good on a major piece of the so-called plan just filed to charge 54% more to build their offshore wind farms. “  This post estimates that these costs combined with all the other authorized but as yet unaccounted for ratepayer costs will be extraordinarily high.

The percentage of residential electric bill costs to meet the Climate Act mandates will increase such that between 8% and 21% of bills cover offshore wind costs and other mandates. The only reason that the public is not grabbing pitchforks and torches to march on Albany in protest of these regressive cost increases is that the public is unaware of what is coming. I am extremely disappointed that politicians and the media have not stepped up and demanded transparent accounting of expected Climate Act costs.

Climate Act Coercion

I recently described the New York State Comptroller’s Office Renewable Electricity in New York State Review and Prospects report (“Comptroller Report”) that addressed progress and prospects for attaining New York’s Climate Leadership & Community Protection Act (Climate Act) 2040 mandate for a zero-emissions electric grid.  This post addresses the following quote from that report: “the Enacted Budget for SFY 2023-24 included a provision to hold the electric bills of low-income customers to 6 percent of household income if the customers participate in State programs to electrify home heating and appliances and undertake efficiency upgrades.”

I have been following the Climate Act since it was first proposed, submitted comments on the Climate Act implementation plan, and have written over 350 articles about New York’s net-zero transition.  I have devoted a lot of time to the Climate Act because I believe the ambitions for a zero-emissions economy embodied in the Climate Act outstrip available renewable technology such that the net-zero transition will do more harm than good.  The opinions expressed in this post do not reflect the position of any of my previous employers or any other company I have been associated with, these comments are mine alone.

Climate Act Background

The Climate Act established a New York “Net Zero” target (85% reduction and 15% offset of emissions) by 2050.  It includes an interim 2030 reduction target of a 40% reduction by 2030 and a requirement that all electricity generated be “zero-emissions” by 2040. The Climate Action Council is responsible for preparing the Scoping Plan that outlines how to “achieve the State’s bold clean energy and climate agenda.”  In brief, that plan is to electrify everything possible and power the electric grid with zero-emissions generating resources.  The Integration Analysis prepared by the New York State Energy Research and Development Authority (NYSERDA) and its consultants quantifies the impact of the electrification strategies.  That material was used to write a Draft Scoping Plan.  After a year-long review the Scoping Plan recommendations were finalized at the end of 2022.  In 2023 the Scoping Plan recommendations are supposed to be implemented through regulation and legislation. 

The provision mentioned in the Comptroller Report that conditionally limits electric bills of low-income customers to 6 percent of household income is an example of the programs that are being implemented to reach the Climate Act targets.  Until reading the quote I was unaware of this new law.  The condition “if the customers participate in State programs to electrify home heating and appliances and undertake efficiency upgrades” caught my attention and spurred this post.

Energy Affordability Program

The FY24 Enacted Budget included the following funding within the Public Service Commission’s Aid to Localities Budget (A.3003-D of 2023, signed Chapter 53 of 2023).  The Energy Affordability Program is allocated $200 million in new funding for utility bill relief for residential customers that do not currently qualify for the Department of Public Service’s current energy affordability policy program, but whose income is below the State median income. The Public Service Commission is directed to consider the feasibility of using area median income or other eligibility thresholds in the event the use of State median income prevents reaching all households that have an energy burden greater than 6%. In addition to Statewide residents, residential customers of electric corporations regulated by the Public Service Commission (PSC) and the Long Island Power Authority, and its service provider Public Service Enterprise Group-Long Island (PSEG-LI) are eligible to participate in the program. This appropriation may be disbursed to utilities, including LIPA, and then disbursed to ratepayers.

The Department of Public Service (DPS) is directed to provide an energy affordability guarantee to residential customers participating in home electrification efforts through the New York State Energy Research and Development Authority (NYSERDA)’s EmPower Plus Program such that EmPower Plus participants pay no more than 6% of household income on utility bills for the duration of the estimated useful life of an EmPower Plus electrification project.  DPS is authorized and directed to establish a cap on such customers’ energy usage applicable to the guarantee.

Discussion

Whenever I start researching a new topic for a blog article about the Climate Act, I have found that it is more complicated and leads to more questions than I had expected.  This topic was no exception.  In this case several things came up.  I was not aware of the Department of Public Service’s current energy affordability policy program.  There is a reference to a six percent energy burden target that I have seen elsewhere but have yet to find what I think represents an official definition or any status data.  I have heard of the EmPower program but never looked into it.  My primary concern is the conditional statement that is associated with EmPower program eligibility for a price guarantee.  I will address these below.

The Energy Affordability Working Group  August 15, 2023Status Report explains how this group associated with the energy affordability policy program was formed:

On August 12, 2021, the Commission issued its Energy Affordability Policy Phase 2 Order (Phase 2 Order) adopting certain modifications and improvements to the energy affordability framework established in the Affordability Order, Implementation Order, and Rehearing Order. Among the improvements to the Energy Affordability Policy directed in the Phase 2 Order, the Commission established an Energy Affordability Policy Working Group (Working Group) that encouraged participation from all interested stakeholders for the advisement of improving energy affordability.  

The working group is associated with two PSC cases: CASE 23-M-0298 In the Matter of Budget Appropriations to Enhance Energy Affordability Programs and  CASE 14-M-0565   Proceeding on Motion of the Commission to Examine Programs to Address Energy Affordability for Low Income Utility Customers.  The status report gives an overview of what they do.

One requirement is a submittal of low-income data to the docket.  On a regular basis Central Hudson Gas and Electric Corporation, Consolidated Edison Company of New York, National Fuel Gas Distribution Corporation, Brooklyn Union Gas Company, Keyspan Gas East Corporation,  Niagara Mohawk Power Corporation, New York State Electric and Gas Corporation, Rochester Gas and Electric Corporation, and, Orange & Rockland Utilities submit data in a proscribed format.  As an example of yet another question that comes up whenever I start digging note this: as far as I can tell the low-income information reports do not cover Long Island electric customers or anyone from the municipal utilities.  I think that is odd but I am not going down that rabbit hole to determine why or if my interpretation is incorrect.

I did combine available data from the most recent reports in a spreadsheet to create the following summary table.  I believe the low-income information reports only cover the participants in the utility Energy Affordability Programs.  If that is the case then the number of participants who are in arrears and the amounts owed  under estimates the state totals.  It is worrisome enough that 155,626 people were sent termination notices and their amount owed is $178.7 million.  The $200 million in this law would barely cover the emergency assistance needed of those people. 

PSC Energy Affordability Submittal Summary

I have seen references to a six percent energy burden target before but not as an official policy.  For example, a recent legislative proposal included a requirement for state agencies to identify policies to ensure affordable housing and affordable electricity (defined as electricity costs no more than 6% of a residential customer’s income) for all-electric buildings.  Alternatively, Addressing Energy Poverty in the US offers other possible criteria:

According to the U.S. Department of Energy, the average energy burden for low-income households is 8.6%. That is three times higher than for non-low income households, which is about 3%.  And according to the Kleinman Center for Energy Policy at University of Pennsylvania, more than one-third of US households are experiencing “energy poverty,” having difficulty affording the energy they need to keep the lights on and heat and cool their home. 

In my opinion there are two issues with the six percent electric burden criterion.  It appears to only apply to all-electric homes and that ignores the needs of people who heat their homes with other fuels.  With regards to the rural poor, the urban politicians who support the Climate Act overlook the fact that many people live in remote rural areas because that is the only location where they can afford housing.  As a result, transportation costs are a major part of their energy budgets because they must travel longer distances to work.

There is another problem with the energy burden criterion.  I have been unable to find where the state stands relative to the six percent target or any other energy poverty criterion  As part of a total energy transition, it seems obvious that we need a baseline status so that we can track whether the program is forcing more people into energy poverty.  The necessary data to calculate the status are not included in the energy affordability policy program reports and I could not find any summary that included it.

The impetus for this post was the condition that in order to get support for an energy affordability guarantee, customers must “participate in State programs to electrify home heating and appliances and undertake efficiency upgrades.”  I am concerned that the rural poor are being overlooked in low-income support programs and this is a specific example.  I recall that there was a qualifying statement in the Draft Scooping Plan that noted that some residential building shells could not be upgraded because of the building type or historical significance.  For example, consider that the Integration Analysis assumes that building shell upgrades are not possible for mobile homes.  Without building shell upgrades, air-source heat pumps are not a viable heating option.  Does that mean that residents in mobile homes or other structures that cannot be improved are not eligible for these benefits?

I had to research EmPower program to determine how that condition might be implemented.  According to the webpage:

EmPower+ helps low- and moderate-income households save energy and money toward energy improvements made to their property.  Through EmPower+:

  • Households can receive a no cost comprehensive home energy assessment to pinpoint where energy and dollars are being wasted and receive a customized plan to lower energy usage.
  • No-cost direct install improvements identified during the assessment can be installed by participating program contractors.
  • Households can receive financial discounts on the cost of energy efficiency improvements.

The program is open to income-eligible owners and renters of 1-4 family households.

The eligibility guidelines do not mention anything related to feasibility.  The eligibility guidelines webpage notes:

Homeowners and renters must meet income requirements to qualify for EmPower+. You may be eligible if you can answer “yes” to these statements:

My household income is below 80 percent of the State/Area Median Income or lower
OR
I reside in a single family home located in a geographically eligible territory
OR
I participate in a utility payment assistance program

I think this is an overlooked concern in the legislation.  The energy improvements are contingent upon the comprehensive home energy assessment.  I believe that there will be instances where at least some of the potential electrification options will not be effective replacements.  There may also be situations in rural areas with poor reliability that electrification of any appliance is a safety issue.  It is not clear whether there are any caveats to the requirement that only customers who participate in State programs to electrify home heating and appliances and undertake efficiency upgrades are qualified for the six percent of household income guarantee. There should be assistance programs for people who have participated in the EmPower Plus home energy assessment but may not be able to implement all the home energy improvements.

If any reader can provide insights on these topics, I would appreciate hearing from you.

Conclusion

The Climate Act-related Public Service Commission’s Aid to Localities Budget included in the FY24 Enacted Budget is an example of the myriad laws, regulations, and policies being enacted to implement the Climate Act net-zero transition.  From the start of this process there has been inadequate evaluation of these programs to ensure that they do what they are supposed to do without unintended consequences.

In this instance, I object to the implicit coercion that there will be a guarantee that the energy burden will not exceed six percent only if customers participate in State programs to electrify home heating and appliances and undertake efficiency upgrades.  It appears the authors of the law did not consider the fact that Integration Analysis admits that not all residences can be electrified effectively and safely or that there are limitations on efficiency upgrades.  If there are no relevant caveats to implementation, then needy low-income citizens will be adversely affected.

Even if my interpretation is wrong and this is not a potential issue, there is a serious shortcoming in the implementation process.  There is not official energy poverty metric that covers all energy use and there is no status data available for the frequently referenced six percent electric bill target.  How will we know if there are increasing energy poverty issues associated the transition unless someone is tracking it?

More on the Enormous Ratepayer Costs of the Climate Act

Earlier this week I published an article about the enormous ratepayer costs of the Climate Leadership & Community Protection Act (Climate Act).  The basis of that article was the Public Service Commission (PSC) first annual informational report on the implementation of the Climate Act.  This article documents cost impacts of the Climate Act in the evidentiary hearing comments for the  New York State Electric & Gas Corporation and Rochester Gas & Electric rate cases. 

I have been following the Climate Act since it was first proposed, submitted comments on the Climate Act implementation plan, and have written over 350 articles about New York’s net-zero transition.  I have devoted a lot of time to the Climate Act because I believe the ambitions for a zero-emissions economy embodied in the Climate Act outstrip available renewable technology such that the net-zero transition will do more harm than good.  The opinions expressed in this post do not reflect the position of any of my previous employers or any other company I have been associated with, these comments are mine alone.

Background

The Climate Act established a New York “Net Zero” target (85% reduction and 15% offset of emissions) by 2050.  It includes an interim 2030 reduction target of a 40% reduction by 2030 and a requirement that all electricity generated be “zero-emissions” by 2040. The Climate Action Council is responsible for preparing the Scoping Plan that outlines how to “achieve the State’s bold clean energy and climate agenda.”  In brief, that plan is to electrify everything possible using zero-emissions electricity. The Integration Analysis prepared by the New York State Energy Research and Development Authority (NYSERDA) and its consultants quantifies the impact of the electrification strategies.  That material was used to develop the Draft Scoping Plan.  After a year-long review, the Scoping Plan recommendations were finalized at the end of 2022.  In 2023 the Scoping Plan recommendations are supposed to be implemented through regulation and legislation.  In addition, as the utilities determine what expenditures are necessary to support the Climate Act goals those costs are incorporated into their rate case requests.

Before the utilities in New York were de-regulated there were seven vertically integrated utility companies serving New York.  Even though those companies have been re-organized the rate case proceedings are based on the original service territories.  Subsequent to de-regulation New York State Electric & Gas (NYSEG) and Rochester Gas & Electric (RG&E) were purchased by Spanish owned Iberdrola and both companies are now in Avangrid.   Avangrid Networks, Inc. is a subsidiary of Avangrid, Inc. and “combines the resources and expertise of eight electric and natural gas utilities with a rate base of $11.7 billion, serving 3.3 million customers in New York and New England.” This article documents post

hearing comments related to the NYSEG electric rate case 22-E-0317, RGE electric rate case 22-E-0319, the NYSEG gas rate case 22-G-0318, and the RGE gas rate case 22-G-0320 that address Climate Act costs.

Evidentiary Hearing

The Department of Public Service (DPS) hearing brief explains the purpose of the evidentiary hearing:

An evidentiary hearing was held in these proceedings on July 17, 2023 and July 18, 2023. The

purpose of the hearing was to receive into evidence and evaluate the Joint Proposal (JP) filed on June 14, 2023. The hearing also provided an opportunity to consider the reasonableness of the JP and develop the record to determine whether the JP is in the public interest in accordance with the Settlement Guidelines of the New York Public Service Commission (Commission). At the hearing, Alliance for a Green Economy (AGREE), Multiple Intervenors (MI), Public Utility Law Project (PULP), AARP, Fossil Free Tompkins (FFT), and Ratepayer and Community Intervenors (RCI) conducted limited cross-examination of the Department of Public Service Trial Staff (Staff) and the New York State Electric & Gas Corporation (NYSEG) and Rochester Gas and Electric Corporation (RG&E; collectively, the Companies) Panel who testified in support of the JP.

The hearing addressed specific issues raised by the parties.  I am going to focus on the MI’s cross-examination concerning the affordability of the revenue requirements and other comments related to affordability.

DPS Hearing Brief

The DPS hearing brief argued that the JP helps customers with affordability by mitigating the revenue requirement (Note that all the footnote references have been excluded for clarity):

At the evidentiary hearing, MI’s cross-examination implied that Staff did not adequately consider affordability as part of its analysis of the provisions contained in the JP. Furthermore, MI questioned whether Staff was “aware of the relative economic conditions impacting …your handling of these rate proceedings?” In fact, the JP addresses affordability by: 1) reducing the Companies’ proposed expenditures from their initial filing; 2) accelerating the amortization of the excess depreciation reserve (EDR); and 3) phasing in a necessary increase in storm reserve rate allowance over the term of the rate plan. These provisions significantly reduce the revenue requirement to make the rates more affordable for customers.

The DPS explanation claims that the “proposed revenue requirement increases in the current cases are largely due to the impact of the Covid-19 pandemic (Pandemic) during the Companies’ last rate cases.”  During the Pandemic the PSC reduced rate increases “to help customers who were facing economic upheaval by limiting rate increases to less than two percent total bill impact in each rate year of the rate plan”. To achieve this reduction, the PSC cut cost recovery for “energy efficiency program and vegetation management spending; limited recovery of certain storm regulatory assets by extending the time period over which the costs would be amortized; and passed back several regulatory liabilities to customers in an expeditious time period.”  They note:

These efforts were warranted given the magnitude of the economic impacts that the Companies’ customers faced at that time, however, these costs and resulting build up of regulatory assets at both NYSEG electric and RG&E electric now have to be addressed in the current proceeding. Although there are unavoidable rate drivers in these cases, Staff has worked diligently to mitigate the impact of the revenue requirements on customers, which is reflected in the JP.

The DPS staff claims that they reduced the revenue requirements in several ways.  NYSEG and RGE have reduced discretionary capital expenditures. They “reprioritized the Companies’ electric capital budget and delayed several infrastructure projects that do not address immediate safety and reliability needs.”  The DPS brief notes states that “When compared to the initial filing, the JP reflects a reduction to the requested electric capital budget from 2024 through 2026 by $2.28 billion for NYSEG and $280.59 million for RG&E.”  My interpretation of this is that these projects will still be needed in the future so they are just being delayed so that this rate increase is not so bad.

Another major cost savings related to vegetation management programs.  These programs are needed to improve system reliability and reduce tree-related outages.  The JP proposes a vegetation management program that sets NYSEG on a longer cycle of vegetation trimming projects.  There is a tradeoff here between the desire to reduce outages and costs.

The JP also utilizes additional excess depreciation reserve (EDR) funds to reduce revenue requirements and help address affordability for customers. This looks like accounting magic to reduce costs but the brief claims that they will be “within the 10% band commonly accepted by the Commission.”   It goes on to say “Using any additional EDR could negatively impact the Companies’ credit ratings and would lead to an inevitable sharp rate increase or a hockey stick in subsequent rate cases, when there simply is not any additional EDR that can be used.”

In another example of accounting magic to keep the costs down the JP changes the major storm Operations and Maintenance (O&M) expense allowance to lessen the impact on customers. If there is a major storm and more money is needed than set aside this will come back and result in less timely storm restoration.  “Although the revenue requirement allowances for major storm restoration should be much higher based on historical levels experienced at the Companies, Staff supports the inclusion of a lesser amount to mitigate the immediate rate impact on customers.

The DPS brief concludes that “even with the proposed increases, the rates for residential customers of both Companies will remain among the lowest in the State, which demonstrates that the provisions referenced above will help to keep rates affordable for customers.”

Conspicuous by its absence was any mention of Climate Act spending.

Climate Act Spending

The costs associated with the Climate Act were not a subject of the evidentiary hearing.  In order to estimate those costs I relied on the June 29, 2022 Technical Conference presentation.  I did not try to determine if the costs in this initial proposal are still the same as what ended up in the final rate case but I believe the results are indicative.  The following slide lists capital expenditure estimates that includes costs for the Climate Act.

The important part of the slide is the following excerpt.

The following table calculates the total and lists percentages for each program. 

There are three capital expenditure programs that are directly associated with the Climate Act.  The Electric and Common Capital Expenditures Testimony describes plans.  The following plans were associated with the search term “CLCPA” that I think are included in the CLCPA category:

  • CLCPA Transmission Projects Phase 1
    • Project Description: The CLCPA Phase 1 Transmission Projects consist of 23 projects for the purpose of unlocking transmission-connected renewable resources by increasing headroom on the system.
  • CLCPA Transmission Projects Phase 2 “Areas of Concern”
    • Project Description: The CLCPA Phase 2 “Areas of Concern” Transmission Projects consist of 46 projects for the purpose of unlocking an incremental amount of transmission-connected renewable resources and to increase headroom on the system.
  • Low Income Clean Generation
    • Program Description: This project will develop one or more solar photovoltaic (“PV”) facilities at both NYSEG and RG&E. NYSEG will install 50 MW of installed capacity while RG&E will install 20 MW of installed capacity
  • EV Charging Hub Project
    • Project Description: This project is a large-scale, purpose-built facility that will serve 10 corridor charging needs for light-duty, medium-duty, and heavy-duty vehicles within the NYSEG service area.

The other two programs are Make Ready and Ithaca Electrification. Make Ready supports electric vehicle (EV) charging infrastructure:” With our new Make-Ready Program, businesses can now quickly install electric vehicle (EV) charging stations with up to 100 percent reimbursement of costs for the electrical improvements needed to support EV charging.”  The Ithaca Electrification project is described as local transmission and distribution projects needed to  address existing reliability needs and will help to support timely execution of the City of  Ithaca’s electrification initiative.”  The following might be another description of this initiative.

In addition to the capital expenditure projects other clean energy initiative within the rate case were described that support the Climate Act.

Another major Climate Act initiative is energy efficiency support.  The presentation describes the associated costs as follows:

These energy efficiency programs are part of a New York State Energy Research & Development Authority program.  New Efficiency: New York (NE:NY) is a “comprehensive mix of strategies to support building developers, commercial and institutional building owners, industrial facilities, and residential households to pursue improvements that reduce energy consumption across the State. These efficiency improvements will enable New York to meet an ambitious new target of 185 trillion Btus (British thermal units) of end-use energy savings below the 2025 energy-use forecast. That’s equivalent to saving the energy consumed by 1.8 million New York homes.”

Apparently DPS staff had an issue with the proposed costs and this was an issue during negotiations.  The following table shows the differences.

Affordability Issue

Three parties addressed affordability. The Public Utility Law Project of New York, Inc. (PULP) post-hearing brief described the JP rate increases as a ratepayer  “affordability crisis”.  AARP New York called the rate increases “unjust and unreasonable”.  Multiple Intervenors commented that the “delivery rate increase are enormous” and “unprecedented”. 

Multiple Intervenors argued that the delivery rate impacts are magnitudes higher than the impacts that the Commission previously found to be unacceptably high and included the following summary table of impacts.  The cumulative percentage total reflects the fact that the first rate-year is in effect for all three years, the second rate-year is in effect for two years, and the final rate-year is in effect for one year.  That approach projects that NYSEG electric delivery rates will be double the current rate in three years

Safety Valve

None of the comments raised the safety valve conditions for affordability in New York Public Service Law  § 66-p (4). “Establishment of a renewable energy program”.   §66-p (4) states: “The commission may temporarily suspend or modify the obligations under such program provided that the commission, after conducting a hearing as provided in section twenty of this chapter, makes a finding that the program impedes the provision of safe and adequate electric service; the program is likely to impair existing obligations and agreements; and/or that there is a significant increase in arrears or service disconnections that the commission determines is related to the program”. 

Unfortunately, the Hochul Administration has never defined these criteria which I believe should have been a primary responsibility of the Climate Action Council.  The criteria used to define “safe and adequate electric service” and “significant increase in arrears or service disconnections” should be defined so that proceedings like this have acceptability limits.   

Multiple Intervenors expressed the frustration of ratepayers relative to the desire to support the Climate Act within certain bounds of affordability:

Multiple Intervenors supports reasonable efforts to maintain, if not improve, electric and gas reliability and customer service, and reduce greenhouse gas emissions. Significantly, however, customers of all types need to be able to afford electric and gas service, and that is where the Joint Proposal fails miserably. Although Multiple Intervenors identified many specific areas of concern regarding the Joint Proposal in prior submissions, it is not in a position to unilaterally rebalance often-competing priorities to fix the Joint Proposal’s numerous shortcomings. Rather, that authority and responsibility rests solely with the Commission. Multiple Intervenors urges the Commission to (i) conclude that the balancing of priorities reflected in the Joint Proposal fails to weigh affordability concerns adequately, and (ii) take decisive action to ensure that delivery rate impacts are moderated to acceptable levels. This is no “ordinary” Joint Proposal, the Commission needs to reject or modify it to protect customers from excessive delivery rate impacts.

Climate Act Cost Discussion

The rationale for the increased costs ignores the costs of the Climate Act.  I did not find specific information in the Proceeding documentation that summarized all the costs.  Note, however, that most of the capital expenditures are related to Climate Act costs which I believe are primarily due to transmission upgrades necessary to get solar and wind project energy to where it is needed.   As an aside the primary place it is needed is New York City so Upstate ratepayers are paying to support that need. The bottom line for the Climate Act portion of the capital expense in rate year 4/23 to 3/24 is $603 million of $1,085 million (56%) total.  If the costs for advanced metering infrastructure (smart meters) are included as Climate Act costs which I believe is appropriate the rate year costs are $713 million or 66% of the total.

JP Climate Act Implementation

I believe that a major problem with Climate Act implementation is that the vast sums of money attract crony capitalists and rent-seeking opportunists all eager to take advantage of the money.  This money is going to come out of the pockets of New Yorkers so these grifters need to be called out.  The parent company of NYSEG and RGE is a good example of a company taking advantage of the Climate Act to reduce their risks and make money.

Iberdrola brags about their commitment:

The Iberdrola group has undergone a profound transformation, anticipating the current energy transition by 20 years to meet the challenges of climate change and the need for a clean, reliable and smart business model.

Today, it is a leader in renewables and smart grids, has a diversified portfolio of businesses and geographies, is present in highly rated countries and has demonstrated its financial strength, expertise and execution capabilities. Furthermore, 90% of the group’s long-term investment plan is aligned with the green investment criteria included in the EU taxonomy.

Briefing comments show how they are trying to fleece ratepayers under the guise of supporting the energy transition.  Commenters argued that the proposed earning adjustment mechanism, incentive awards for non-wires alternatives and procurement of environmental attributes, and treatment of Climate Act-related capital expenditures all increase the rate case request at the expense of consumers.

This article is already too long so I am not going to delve into specifics of all these adjustments.  One example will have to suffice.  PULP addressed the 9.2% return on equity (ROE) included in the JP.  ROE is considered a gauge of a corporation’s profitability and how efficient it is in generating profits. PULP explains:

The Companies are looking to increase from the current ROE of 8.8%, to the 9.2% ROE, which substantially adds to the already historic rate increases included in this JP. PULP generally urges careful consideration of every aspect of the JP when looking for ways to cut costs. Specifically, we urge the ALJs and the Commission to modify the JP so that the ROE is not set through confidential settlement negotiations, but rather through calculations using the generic finance model, while also providing for an annual recalculation.

The PULP comment argues that uncertainties associated with the Climate Act are not an appropriate reason to increase the ROE as asserted in the JP.  They note that it is “reasonable to assume that the risks presented by the CLCPA would be addressed in a manner that is consistent with past Commission policy that utilities should be able to recover all their operating costs and an adequate return on their investments, assuming efficient and economical management”.  Cynics like me look at this kind of sweetheart deal and wonder if this part of the political calculus of the Climate Act.  The utilities that know that there are enormous affordability and reliability risks for the net-zero transition get a bit more profit for not speaking up about those risks.

Conclusion

The bottom line is that Climate Act costs are a major factor in the extraordinarily large rate case request.  No one has stepped up to say that this is an issue in this instance and every future rate case for every New York utility is going to have to have similarly large costs.

Public Service Law §66-p (4) requires consideration of affordability and reliability for Climate Act implementation but the specific criteria have not been defined.  New York GHG emissions are less than one half of one percent of global emissions and global emissions have been increasing on average by more than one half of one percent per year since 1990.  The Hochul Administration has no plan in place to address affordability.   As a result, New York emission reductions are not going to affect climate change, so it is unacceptable to prove that affordability and reliability considerations are not adversely affected.

The PULP briefing notes that recent collection activity reports are a good indication of whether residential customers are currently able to pay their bills.  They note:

Unfortunately, these numbers are striking. As of June 2023, 130,637 residential NYSEG accounts were behind on their payments by 60-days or more, for a total of $79.3 million. For RG&E, 78,112 residential accounts were behind on their bills for a total of $61.8 million.

It is unimaginable to me that any reasonable affordability criterion defined per Public Service Law §66-p (4) would find that these rate case impacts would be acceptable.  The PSC should temporarily suspend or modify the obligations of the Climate Act until we have a better understanding of the costs to implement the Act.

Climate Act Ratepayer Costs Will be Enormous

I sent a link to my All Otsego commentary Zero Emissions Transition Realistic to my distribution list and received some feedback that prompted this article.  The commentary noted that the Public Service Commission’s first annual informational report on the implementation of the Climate Leadership & Community Protection Act (Climate Act) included the first admission of ratepayer costs.  It mentioned that more costs were coming but I did not estimate specific ratepayer impacts and the feedback suggested that information would be useful.  .  In the worst case, my analysis estimates that upcoming Climate Act related costs for every utility in the state will be greater than the total current monthly bill.

I have been following the Climate Act since it was first proposed, submitted comments on the Climate Act implementation plan, and have written over 300 articles about New York’s net-zero transition.  I have devoted a lot of time to the Climate Act because I believe the ambitions for a zero-emissions economy embodied in the Climate Act outstrip available renewable technology such that the net-zero transition will do more harm than good.  The opinions expressed in this post do not reflect the position of any of my previous employers or any other company I have been associated with, these comments are mine alone.

Climate Act Background

The Climate Act established a New York “Net Zero” target (85% reduction and 15% offset of emissions) by 2050.  It includes an interim 2030 reduction target of a 40% reduction by 2030 and a requirement that all electricity generated be “zero-emissions” by 2040. The Climate Action Council is responsible for preparing the Scoping Plan that outlines how to “achieve the State’s bold clean energy and climate agenda.”  In brief, that plan is to electrify everything possible using zero-emissions electricity. The Integration Analysis prepared by the New York State Energy Research and Development Authority (NYSERDA) and its consultants quantifies the impact of the electrification strategies.  That material was used to develop the Draft Scoping Plan.  After a year-long review, the Scoping Plan recommendations were finalized at the end of 2022.  In 2023 the Scoping Plan recommendations are supposed to be implemented through regulation and legislation.  In 2024, and every two years thereafter, there will be a program review of the progress in meeting the overall targets for deployment of renewable energy systems and zero emission sources and annual funding commitments and expenditures.

According to the Public Service press release:

The Climate Act’s directives require the Commission to build upon its existing efforts to combat climate change through the deployment of clean energy resources and energy storage technologies, energy efficiency and building electrification measures, and electric vehicle charging infrastructure. In recognition of the scale of change and significant work that will be necessary to meet the Climate Act’s aggressive targets, the Commission directed DPS staff to assess the progress made in line with its directives under the Climate Act and to provide guidance, as appropriate, on how to timely meet the requirements of the Climate Act.

The Scoping Plan does not provide any ratepayer cost impacts but the New York State Department of Public Service First Annual Informational Report on Overall Implementation of the Climate Leadership and Community Protection Act (Informational Report”) does provide estimates for 2022.  I have published three articles about the Informational Report: first impressions,  a comparison of the goals in the report and the New York Cap-and-Invest (NYCI) Program Reference Case with respect to affordability implications of the Informational Report and NYCI.

Ratepayer Impacts in Informational Report

Much of the information in this section was previously published here.  I converted the tables in the Informational Report to a spreadsheet so that I could combine the data from multiple tables.  Three tables are of particular interest: Table 4: 2022 Electric CLCPA Recoveries, Table 7: 2022 Typical Monthly Electric Bills with CLCPA related costs disaggregated, and Table 8: Authorized Funding to Date.

Table 4: 2022 Electric CLCPA Recoveries summarizes costs recovered in 2022 by utilities for electric programs.  The costs recoveries include: CES (electric only), CEF (electric only), certain VDER (electric only), Electric Vehicle Make Ready Program (electric only), Clean Heat programs (electric only), Integrated Energy Data Resource (electric only), and Utility Energy Efficiency programs (electric and gas). The table states that $1,175,788,000 in Climate Act costs were recovered in 2022.  In the context of total ratepayer costs note that transmission upgrades are not included in the 2022 estimates and that there also are gas costs that are relatively small.

Table 7: 2022 Typical Monthly Electric Bills with CLCPA related costs disaggregated is the first admission by the Hochul Administration of potential costs of the Climate Act to ratepayers.  The basis for the typical electric delivery and supply bills for 2022 was provided for the following customer types:

A.           Residential customers (600 kWh per month),

B.           Non-residential customers (50 kW & 12,600 kWh per month),

C.           Non-residential customers (2,000 kW & 720,000 kWh per month), and

D.           Non-residential high load factor customers (2,000 kW & 1,296,000 kWh per month).

PSC Staff requested that utilities disaggregate the cost components reported in Table 2 (electric) to determine CLCPA related impacts on customers as shown in Table 7.  Climate Act costs added between 9.8% and 3.7% to residential monthly electric bills in 2022.

The Climate Act costs in 2022 are just the start of eventual costs to consumers.  Table 8: Authorized Funding to Date “gives a sense” of expenditures that will ultimately be recovered in rates. The Informational Report explains:

This annual report is a review of actual costs incurred by ratepayers to date in support of various programs and projects to implement the CLCPA and does not fully capture potential future expenditures, including estimated costs already authorized by the Commission but not yet recovered in rates. To complement this overview of cost recoveries incurred to date, we also present below a table of the various programs and the total amount of estimated costs associated with each authorized by the Commission to date. Table 8 gives a sense of expenditures that ratepayers could ultimately see recovered in rates. These values are conservative and reflect both past and prospective estimated costs.

It is important to note that the Commission authorized some of the estimated costs in Table 8 prior to CLCPA enactment and that the cost associated with these authorized programs will be recovered over several years to come, based on the implementation schedules for these projects or programs and will mitigate the cost impacts to ratepayers year over year. These estimated costs represent either total program budget, estimated total cost for the program over its duration, or costs incurred to date in support of the program. Additionally, these initiatives will result in a variety of other changes that will impact how much consumers pay for energy. A number of these would put downward pressure on costs, including benefits in the form of reduced energy usage and therefore reduced energy bills to consumers. The Department has also previously described market price effects that are a result of these investments. When load is reduced or more low-cost generation is added, it would be anticipated that energy prices would fall because the market would rely less on higher cost generators. In addition, investments in transmission infrastructure not only unbottle renewable energy but also yield production cost savings and reliability benefits.

In sum, the total estimated costs associated with these programs or projects should not be considered as entirely incremental costs to what ratepayers would otherwise pay. Subsequent annual reports may include additional information about costs recovered relative to the funding previously authorized by the Commission in these programs, including funds already expended in support of these programs.

The takeaway message from Table 8 is that the authorized funding to date of program costs that will eventually make their way to ratepayer bills totals $43.756 billion.  Note that the spreadsheet version of this table details the footnote costs.

Future Ratepayer Impacts

The ratio of the authorized Climate Act funding to date ($43.8 billion) to the Climate Act costs that have been authorized and were in the 2022 residential bills ($1.2 billion) is 37.2.  It is tempting to simply multiply the ratio by each of the monthly Climate Act disaggregated cost components reported by the utilities to determine CLCPA future related impacts on customers. However, this will not give an exact utility-specific estimate because the money authorizations per utility for 2022 and the future will not necessarily be the same.  For example, earlier this year I wrote about the PSC approving requests to develop 62 local transmission upgrades that would alleviate congestion on the transmission system to get power to NYC from wind and solar projects upstate.  The transmission upgrade projects will cost $4.4 billion to support 3.5 GW of renewable energy.  The estimated bill impacts were not the same for each utility because costs were a function of where the upgrades were located.  At this time no one knows how the costs will be allocated amongst the utilities. 

In addition, the costs will not be allocated all at once.  There is no documentation that explains the annual 2022 allocations relative to the total costs of each program.  In the worst case all the costs could be allocated in a single year.

In order to give a rough idea, I used a lower ratio.  The following table gives a conservative estimate of future costs by using a ratio of 30.  I multiplied the ratio of 30 by the 2022 utility-specific monthly Climate Act related costs to estimate the future Climate Act costs.  The future total monthly bill equals the 2022 bill minus the 2022 Climate Act related costs plus the future authorized funding Climate Act cost estimated as 30 times the 2022 costs.

Summary of Ratepayer Costs

The informational Report notes that. Climate Act costs that have been authorized and were in the 2022 residential bills total $1.2 billion.  The Report notes that in 2022 the costs already associated with the Climate Act increased the Upstate residential monthly electric bills 7.6% or $7.15 per month for NYSE&G customers; 7.7% or $7.54 for RG&E customers; and 9.8% or $9.38 for Niagara Mohawk customers.  

The report does not attempt to project future ratepayer costs of the authorized Climate Act funding to date that total another $43.8 billion.  Using the conservative ratio of 30 and assuming a similar distribution of costs per utility and that all costs will be in one year, I estimate that the monthly ratepayer costs associated with the Climate Act will total at least $214.50 for NYSE&G consumers, $226.50 for RG&E customers, and  $281.40 for NMPC customers.  The Climate Act related costs for every utility in the state will be greater than the total current monthly bill.

Discussion

In two recent articles I explained why the claims that the net-zero transition will result in cheaper electricity are rubbish.  The claim that wind and solar are cheaper is only possible if you ignore all the additional costs necessary to get the energy to consumers when and where needed.  In another post I explained arguments that solar and wind are only cheaper than fossil fuels in at most a small fraction of situations and for the overwhelming majority of the world’s energy needs, solar and wind are either completely unable to replace fossil fuels or far more expensive.  These ratepayer costs are for some of the many other services and support necessary to integrate wind and solar into a “zero-emissions” electric grid.  I suspect that future additional costs will be at least an order of magnitude higher.

Unfortunately, these are not the only costs for New Yorkers.  The Scoping Pan proposes to electrify everything possible.  These costs do not include what it will take to electrify home heating, cooking, clothes drying and hot water heating.  Nor does it include the costs for home electric vehicle chargers or the very likely need to upgrade the electric service to the residence when everything is electrified.  In addition to electrification of the home there will be the costs for an electric vehicle.

These estimated costs are high, but there is no escaping the fact that ratepayers are on the hook for an additional $43.8 billion in Climate Act costs.  I admit that the distribution of costs is unlikely to be as concentrated as I have assumed.  The absence of an estimate in the PSC report suggests that even if the eventual ratepayer impact is lower, it is still significant.

Conclusion

New York GHG emissions are less than one half of one percent of global emissions and global emissions have been increasing on average by more than one half of one percent per year since 1990.  These facts coupled with the extraordinary costs noted in the PSC Informational Report suggest that it is time to step back and wrest control of New York’s energy future from the innumerate ideologues who have foisted the Climate Act on New York.

These costs may not mean New York should not do something but it does mean that we have time to re-evaluate the Scoping Plan.  We need determine how much the transition will cost, whether we can maintain current levels of reliability with an electric grid that relies on wind and solar, and determine all the environmental impacts of wind and solar resources at the scale necessary for the net-zero transition before it is too late to prevent an affordability crisis, blackouts, and more damage to the environment from this supposed “cure” than any climate change impacts.

NY Cap-and-Invest Reference Case vs PSC First Annual Informational Report

Two proceedings are dancing around the issue of affordability associated with the Climate Leadership & Community Protection Act (Climate Act or CLCPA) emission reduction mandates.  The New York State Department of Public Service First Annual Informational Report on Overall Implementation of the Climate Leadership and Community Protection Act includes cost estimates for existing programs. The New York State Department of Environmental Conservation (DEC) and New York State Energy Research & Development Authority (NYSERDA) are implementing the New York Cap-and-Invest (NYCI) proposed by Governor Hochul which is a market-based program to raise revenues for the strategies necessary to meet the mandates.  This post compares the costs associated with programs considered in the two proceedings.

I have been following the Climate Act since it was first proposed, submitted comments on the Climate Act implementation plan, and have written over 300 articles about New York’s net-zero transition.  I have devoted a lot of time to the Climate Act because I believe the ambitions for a zero-emissions economy embodied in the Climate Act outstrip available renewable technology such that the net-zero transition will do more harm than good.  The opinions expressed in this post do not reflect the position of any of my previous employers or any other company I have been associated with, these comments are mine alone.

Climate Act Background

The Climate Act established a New York “Net Zero” target (85% reduction and 15% offset of emissions) by 2050 and an interim 2030 reduction target of a 40% reduction by 2030. The Climate Action Council is responsible for preparing the Scoping Plan that outlines how to “achieve the State’s bold clean energy and climate agenda.”  In brief, that plan is to electrify everything possible and power the electric grid with zero-emissions generating resources.  The Integration Analysis prepared by the New York State Energy Research and Development Authority (NYSERDA) and its consultants quantifies the impact of the electrification strategies.  That material was used to write a Draft Scoping Plan.  After a year-long review the Scoping Plan recommendations were finalized at the end of 2022.  In 2023 the Scoping Plan recommendations are supposed to be implemented through regulation and legislation. 

Cap-and-Invest Background

According to the Cap-and-Invest Analysis Inputs and Methods webinar (Inputs and Methods Webinar Presentation and View Session Recording) on June 20, 2023, the New York State Department of Environmental Conservation (DEC) and the New York State Energy Research & Development Authority (NYSE$RDA) are developing the New York State Cap-and-Invest (NYCI) Program to meet the greenhouse gas emission limits and equity requirements of the Climate Act.

The NYCI feedback webinars all included the following slide that describes the program.  Setting a cap is supposed to provide compliance certainty and the revenues generated “will minimize potential consumer costs while supporting critical investments” in the control strategies necessary to meet the Climate Act targets.

NYCI Policy Modeling

The Analysis Inputs and Methods webinar mentioned above described the modeling analyses planned to support the development of the program: “This analytics study will assess potential market outcomes and impact from the proposed New York Cap-and-Invest (NYCI) program.” 

In order to evaluate the effects of different policy options, the Hochul Administration has proposed policy modeling.  This kind of modeling analysis forecasts future conditions for a baseline or “business-as-usual” case, makes projections for different policy options, and then the results are compared relative to the business-as-usual case. I disagree with the presumptions in the proposed modeling associated with which programs should be included.

The Scoping Plan modeling used a reference case that included “already implemented” programs and the NYCI Cap-and-Invest Analysis Inputs and Methods webinar proposed to use the same framework.  Starting with the reference case developed for the Scoping Plan, the NYCI modeling proposed to add policies enacted since then.  This reference case approach is misleading because it under estimates the total cost to meet the Climate Act emission reduction mandates.

I maintain that it is more appropriate to compare the policy cases to a base case that excludes all programs intended to reduce GHG emissions.  NYCI revenues are supposed to “minimize potential consumer costs while supporting critical investments”.  I believe that statement argues that NYCI proceeds are intended to fund all the control programs necessary to meet the Climate Act mandates and not exclude programs that were already implemented.

PSC Informational Report

On July 20, 2023 the first annual informational report (“Informational Report”) on the implementation of the Climate Act was released.  According to the press release:

The Climate Act’s directives require the Commission to build upon its existing efforts to combat climate change through the deployment of clean energy resources and energy storage technologies, energy efficiency and building electrification measures, and electric vehicle charging infrastructure. In recognition of the scale of change and significant work that will be necessary to meet the Climate Act’s aggressive targets, the Commission directed DPS staff to assess the progress made in line with its directives under the Climate Act and to provide guidance, as appropriate, on how to timely meet the requirements of the Climate Act.

The Department of Public Service presentation on the Informational Report notes in the following conclusion slide that “ the estimates of total funding authorized by the Commission to date for various clean energy programs in some instances reflect actions that pre-date the enactment of the Climate Act.”  This is the only reference to “already implemented” programs.  The conclusion states that the information presented “represents  direct effects of CLCPA implementation only, and only the portion of direct effects of programs over which the Commission has oversight authority.”  I interpret that to mean that they are not concerned with which program implements the necessary control strategies but only the results of all the programs relative to the Climate Act mandates. 

The Informational Report also notes that “It is difficult to pull out exactly what costs we would have otherwise incurred for infrastructure investment vs. the cost of CLCPA.”  This is the reason a base case is necessary.  You need some estimate of investments that would have occurred were it not for the policy.  In my opinion if they were worried about the difference between pre-CLPA investment costs vs. CLCPA-mandated investments they would have mentioned it here.   Because the Investment Report does not distinguish between costs for programs that pre-date the Climate Act and programs that are mandated by the Climate Act itself, I conclude that the NYCI modeling analyses should follow that precedent and not include “already implemented” control strategy programs.

Implementation Report Costs

I converted the tables in the Implementation Report to a spreadsheet so that I could combine the data from multiple tables.  Three tables are of particular interest: Table 4: 2022 Electric CLCPA Recoveries, Table 7: 2022 Typical Monthly Electric Bills with CLCPA related costs disaggregated, and Table 8: Authorized Funding to Date.

Table 4: 2022 Electric CLCPA Recoveries summarizes costs recovered in 2022 by utilities for electric programs.  The costs recoveries include: CES (electric only), CEF (electric only), certain VDER (electric only), Electric Vehicle Make Ready Program (electric only), Clean Heat programs (electric only), Integrated Energy Data Resource (electric only), and Utility Energy Efficiency programs (electric and gas). The table states that $1,175,788,000 in Climate Act costs were recovered in 2022.

Table 7: 2022 Typical Monthly Electric Bills with CLCPA related costs disaggregated is the first admission by the Hochul Administration of potential costs of the Climate Act to ratepayers.  The basis for the

typical electric delivery and supply bills for 2022 was provided for the following customer types:

A.           Residential customers (600 kWh per month),

B.           Non-residential customers (50 kW & 12,600 kWh per month),

C.           Non-residential customers (2,000 kW & 720,000 kWh per month), and

D.           Non-residential high load factor customers (2,000 kW & 1,296,000 kWh per month).

PSC Staff requested the utilities disaggregate the cost components reported in Table 2 (electric) to determine CLCPA related impacts on customers.  Climate Act costs added between 9.8% and 3.7% to residential monthly electric bills in 2022.

Table 8: Authorized Funding to Date “gives a sense” of expenditures that will ultimately be recovered in rates. The Implementation Report explains:

This annual report is a review of actual costs incurred by ratepayers to date in support of various programs and projects to implement the CLCPA and does not fully capture potential future expenditures, including estimated costs already authorized by the Commission but not yet recovered in rates. To complement this overview of cost recoveries incurred to date, we also present below a table of the various programs and the total amount of estimated costs associated with each authorized by the Commission to date. Table 8 gives a sense of expenditures that ratepayers could ultimately see recovered in rates. These values are conservative and reflect both past and prospective estimated costs.

It is important to note that the Commission authorized some of the estimated costs in Table 8 prior to CLCPA enactment and that the cost associated with these authorized programs will be recovered over several years to come, based on the implementation schedules for these projects or programs and will mitigate the cost impacts to ratepayers year over year. These estimated costs represent either total program budget, estimated total cost for the program over its duration, or costs incurred to date in support of the program. Additionally, these initiatives will result in a variety of other changes that will impact how much consumers pay for energy. A number of these would put downward pressure on costs, including benefits in the form of reduced energy usage and therefore reduced energy bills to consumers. The Department has also previously described market price effects that are a result of these investments. When load is reduced or more low-cost generation is added, it would be anticipated that energy prices would fall because the market would rely less on higher cost generators. In addition, investments in transmission infrastructure not only unbottle renewable energy but also yield production cost savings and reliability benefits.

In sum, the total estimated costs associated with these programs or projects should not be considered as entirely incremental costs to what ratepayers would otherwise pay. Subsequent annual reports may include additional information about costs recovered relative to the funding previously authorized by the Commission in these programs, including funds already expended in support of these programs.

The takeaway message from Table 8 is that the authorized funding to date of program costs that will eventually make their way to ratepayer bills totals $43.756 billion.  Note that the spreadsheet version of this table details the footnote costs.

The following table (Summary tab in the spreadsheet) combines Table 4: 2022 Electric CLCPA Recoveries and Table 8: Authorized Funding to Date.  This represents my best estimates of where the cost categories coincide but it represents my opinion only.  Given all the caveats in the preceding description I don’t think anyone has a definitive handle on these numbers.  The thing that jumps out is the difference between the relatively paltry $1.176 billion in estimated Climate Act costs collected in 2022 relative to the $43.756 billion in authorized funding.  Table 4 data is for one year and Table 8 data is over multiple years. The caveats in the previous quotation should be kept in mind.

Buried in a footnote is an admission that these are not all the costs authorized.  Footnote 7 in Table 8 states:

Not included in this table is the Propel NY transmission project, selected by the NYISO Board in June 2023 in response to the Commission’s declaration of a public policy transmission need (PPTN) to support injections of offshore wind energy to the Long Island system by 2030 at an estimated cost of $3.36 billion. Since the Commission did not directly approve this project, the estimated cost is not captured in the table above.

The bottom line is that this is just the start of the costs.  The Propel transmission project is one example.  I described this project and its costs earlier this year.  I noted that the costs associated with this project are for 3,000 MW of offshore wind.  The Climate Act goal is for 9,000 MW and the Scoping Plan Integration Analysis projects that 12,675 MW of offshore wind will be needed by 2040 in the Strategic Use of Low-Carbon Fuels mitigation scenario.  If the transmission costs are proportional that would mean that transmission costs will be three to four times higher than the $3.36 billion listed for the program that is not included.  I am sure that there are many more examples of programs that will be needed to satisfy the regulated utility obligations for Climate Act emission reduction mandates.

NYCI Reference Case Scenario

The proposed modeling methodology for NYCI proposes to follow the same policy modeling approach as the Scoping Plan where a business-as-usual baseline is not used as the comparison standard for the policy scenarios.  Instead, they propose to use the Scoping Plan Reference Case described as “Business as usual plus implemented policies” that includes the following:

  • Growth in housing units, population, commercial square footage, and GDP
  • Federal appliance standards
  • Economic fuel switching
  • New York State bioheat mandate
  • Estimate of New Efficiency, New York Energy Efficiency achieved by funded programs: HCR+NYPA, DPS (IOUs), LIPA, NYSERDA CEF (assumes market transformation maintains level of efficiency and electrification post-2025)
  • Funded building electrification (4% HP stock share by 2030)
  • Corporate Average Fuel Economy (CAFE) standards
  • Zero-emission vehicle mandate (8% LDV ZEV stock share by 2030)
  • Clean Energy Standard (70×30), including technology carveouts: (6 GW of behind-the-meter solar by 2025, 3 GW of battery storage by 2030, 9 GW of offshore wind by 2035, 1.25 GW of Tier 4 renewables by 2030)

Business-as-usual in my opinion should only include: growth in housing units, population, commercial square footage, and GDP; Federal appliance standards; and economic fuel switching.  All the other programs only exist as part of electrification strategies to reduce GHG emissions.

The Analysis Inputs and Methods webinar presentation stated that the Scoping Plan’s Reference Case will be updated with policies adopted since the original modeling was completed. The webinar asked for input on which policies to include from the following list:

  • NYC Local Laws
  • Statewide new construction codes
  • IRA Incentives
  • Advanced Clean Cars II/Advanced Clean Trucks
  • 100% sales MHDVs by 2045
  • 100% ZEV school buses by 2035, 100% transit buses by 2040
  • IRA Methane Charge
  • EPA Supplemental Rule
  • NYS Part 203
  • AIM Act (EPA Technology Transitions)

All of these programs also exist solely to reduce GHG emissions.  In order to determine the cost to meet the Climate Act targets they should be included as part of the policy case and not the business-as-usual case.

It can be argued that every line item in Table 8 could be considered part of the proposed Reference Case because some component of each category started before the Climate Act was enacted.  Recall that the Informational Report did not try to differentiate between pre-Climate Act and post-Climate Act programs so there are portions of the programs listed that will likely not be considered appropriate for the reference case.  However, using this definition most of these costs will be in the reference case and I would bet that the rationale and costs will not be documented well enough to determine which specific control programs are included.

One other way to differentiate between pre-Climate Act and post-Climate Act enactment is by the case number.  The first two digits are the year the proceeding began.  In my summary table there is only one case number 20 or higher.  Strategic Use of Energy Related Data (Case 20-M-0082) has $72 million funding authorized to date.  Using this approach, the proposed Reference Case would include $43.684 billion program costs as opposed to the $43.756 billion of total authorized costs.  I believe that they can pick and choose programs to include or exclude based on this reference case approach to satisfy the political motivations of the Hochul Administration.

Discussion

The Scoping Plan has been described as “a true masterpiece in how to hide what is important under an avalanche of words designed to make people never want to read it”.  The quantitative documentation supporting the document hides relevant information even better.  The single number that most New Yorkers want to know is how much will this cost.  The Scoping Plan cost numbers did not answer that question.

I addressed the Scoping Plan cost and benefit numbers in my Draft Scoping Plan comments and the verbal comments I presented at the Syracuse public hearing.  The issues I raised and summarized in this post have never been addressed.  In that post I compared the Scoping Plan cost presentation to a shell game.  A shell game is defined as “A fraud or deception perpetrated by shifting conspicuous things to hide something else.”  In the Scoping Plan shell game, the authors argue that energy costs in New York are needed to maintain business as usual infrastructure even without decarbonization policies but then include decarbonization costs for “already implemented” programs in the Reference Case baseline contrary to standard operating procedure for this kind of modeling.  Shifting legitimate decarbonization costs to the Reference Case because they are already implemented without adequate documentation fits the shifting condition of the shell game deception definition perfectly. 

Anyone who has not spent much time following the Climate Act implementation process might ask why was this done for the Scoping Plan analysis and why is it being proposed for the NYCI modeling analysis.  One of the justifications for the Scoping Plan was that the “costs of inaction are more than the costs of action”.  Shifting implementation costs away from the Climate Act program reduced the costs of actions to the point that they could make that claim.

Why are they doing it again?  One of the great unknowns in the NYCI implementation process is the revenue target.  The rational approach would be to calculate expected total costs, revenues from Federal programs, revenues from utility ratepayers, and personal and business investments for required infrastructure then calculate the difference between costs and those revenues as the amount necessary for the cap-and-invest revenues.  Each of those values is a politically sensitive number that will likely cause public outcry because it is going to be large.  If the NYCI revenue target does not include all the costs necessary to meet the Climate Act targets because those costs are covered elsewhere, then the NYCI modeling can show that the program is “affordable” and will not be a major burden.  Given that this strategy worked for the Scoping Plan “costs of inaction are less then the costs of action” scam I believe they are sticking with a proven strategy.

Conclusion

This past week there were signs of discontent with the potential costs of the Climate Act on utility ratepayer assessments.  Utility bills in New York City will go up significantly next month when Consolidated Edison of New York’s new rate case assessments become effective. Con Ed admitted that renewable energy investments contributed to the cost increases.  “Our customers demand safe and reliable service and increasingly renewable energy. This investment from customers is going to allow us to redesign and rebuild the grid, to move it towards electrification,” Con Ed media relations director Jamie McShane told Fox News Digital.

Comparison of the two state initiatives indicate that these costs are going to get much worse.  The PSC Implementation Report states “The magnitude of change the CLCPA requires is significant and will present challenges related to the need to preserve the resiliency and reliability of the energy systems, and cost mitigation to preserve energy affordability”.  The NYCI modeling assessment proposes to use an inappropriate modeling scenario that hides the true costs of implementation.  I have little doubt that the Hochul Administration analysis team has already determined that this approach is necessary to provide a politically correct NYCI revenue target.

At this point all anyone can do is to ask for a full accounting of the costs and expected emission reductions for all the control strategies necessary to meet the net-zero Climate Act mandate.  This information was not provided in the Scoping Plan but is a prerequisite for the proposed NYCI program.

Finally, note that the costs addressed in the PSC proceeding are ratepayer costs for energy.  The overall strategy for de-carbonization is to electrify everything possible.  The costs for each homeowner to replace their furnace, stove, and hot water heater with an electrical replacement is not included.  There also will be homeowner costs associated with electric vehicles to say nothing of the cost of electric vehicle itself. When everything is added up the costs will be enormous.  I do not think that customer demand for renewable energy is as strong as the desire for affordable energy.  It is past time for the Hochul Administration to supply a full accounting of potential costs to residents and businesses so that people will be able to decide for themselves how much they want to pay.