The New York Independent System Operator (NYISO) 2026 Reliability Needs Assessment (RNA), released November 17, 2026, notes that “Many more projects are currently active in the NYISO interconnection process, including more than 14,000 MW nameplate of solar, wind, and battery storage in the 2024 Transitional Cluster Study, which is nearing completion.” This post describes that interconnection process and explains why I think the numbers say more about the limits of the net-zero transition than its promise.
As a retired air‑pollution meteorologist who has spent a career worrying about both the air people breathe and whether the lights stay on, I am convinced that implementation of the Climate Act net-zero mandates will do more harm than good if the future electric system relies only on wind, solar, and energy storage. I have followed the Climate Act since it was first proposed, submitted comments on the Climate Act implementation plan, and have written over 650 articles about New York’s net-zero transition.
The opinions expressed in this article do not reflect the position of any of my previous employers or any other organization I have been associated with, these comments are mine alone. I acknowledge the use of Perplexity AI to generate summaries and references included in this document.
Overview
The Climate Leadership & Community Protection Act (Climate Act) is often described in broad, aspirational terms, but its mandates are very specific. Public Service Law Section 66‑p requires the Public Service Commission, by June 30, 2021, to establish a program ensuring that at least 70% of statewide electric generation secured by jurisdictional load-serving entities in 2030 comes from “renewable energy systems” and that by 2040 the statewide electrical demand system is zero emissions. Meeting those targets requires tens of thousands of megawatts of new wind, solar, and storage. Every project must get through the NYISO interconnection process.
Interconnection is frequently blamed for slow progress. In 2024 NYISO adopted a cluster study approach to speed things up, and its first cluster is now close to completion. It is a good time to look at what it has produced.
How Interconnection Used to Work
Under the legacy process described in the 2023 NYISO Interconnection Process Report, a developer submitted an interconnection request and the project moved through a sequence of individual studies: a feasibility study, a system impact study, and then a facilities study performed with a group of projects known as a Class Year. Projects of 20 MW or less went through a separate small generator process. The Class Year determined the transmission upgrades needed to connect the group and allocated those costs among the projects.
This serial approach was slow, entry was cheap, and speculative projects clogged the queue. When one dropped out late, everyone else’s cost allocations had to be redone.
The New Cluster Study Process
The Federal Energy Regulatory Commission (FERC) addressed these issues nationally in Order 2023, which required grid operators to adopt a “first-ready, first-served” cluster approach. NYISO’s version is in Attachment HH of its tariff, the Standard Interconnection Procedures, and the overall process is summarized on the NYISO interconnection page. NYISO explained the change in Enhancing the Interconnection Process in August 2024.
The NYISO technical bulletin on the Transition Cluster Study lays out the steps:
- Application window. The transition cluster opened August 1, 2024, with a 75-day window instead of the standard 45 days. Applicants paid a $10,000 non-refundable fee plus a study deposit and had to show site control, workable models, and compliance with inverter-based resource standards.
- Customer engagement window. A 90-day period that screens out physically infeasible projects.
- Phase 1. After a five-business-day entry decision, NYISO and the transmission owners perform roughly 190 days of studies to identify the local upgrades each project needs.
- Phase 2. After a ten-business-day decision, roughly 270 days of additional study, including the deliverability analysis that determines whether a project can count toward capacity requirements.
- Final decision. Each developer accepts its allocated upgrade costs and posts security, or withdraws. When projects withdraw, costs are reallocated and the remaining projects decide again.
NYISO’s April 2025 post, Aspiring Generation Projects Advance Through a New NYISO Interconnection Process, reported that “Approximately 240 generation projects are advancing through the first phase.” Commercial readiness deposits and withdrawal penalties were included “to incentivize uncertain projects to exit the queue early.”
Where the Transition Cluster Stands
The Transition Cluster Study 2024 Phase 2 report, dated August 17, 2026, shows how much the cluster shrank. About 240 projects entered Phase 1. By Phase 2 there were 91 projects requesting 15,531 MW of interconnection service. The RNA counted 87 requests totaling more than 15,000 MW as of September 2026, of which more than 14,000 MW is solar, wind, and battery storage.
The Phase 2 report also puts a price on connecting those projects. Total cost allocations are $1.93 billion: $1.42 billion from Phase 1 local upgrades and $503 million from Phase 2 deliverability and other upgrades. That works out to roughly $124 per kilowatt of requested capacity, just to connect to the grid. Single items are large: $134 million for a STATCOM and related work at the Watercure 345 kV substation and $132 million for Long Island 69 kV rebuilds. Many estimates carry an uncertainty range of minus 15% to plus 30%.
Developers have 30 days after Operating Committee approval to accept or reject their allocations, with further rounds whenever someone drops out. The cluster opened August 1, 2024, so even the streamlined process has taken well over two years to reach this point. A second cluster is already underway: the RNA notes that 52 new requests totaling more than 12,000 MW are in the initial stages of the 2026 Cluster Study.
Completing Interconnection Is Not Getting Built
The key point is that finishing the interconnection process does not mean a project gets built. NYISO made this point itself in an August 21, 2025 post, Since 2019, Clean Energy Projects Totaling More Than 14,000 MW Have Completed the Interconnection Process. Note that this is a different 14,000 MW from the Transition Cluster figure. NYISO reported that “106 projects representing more than 14,000 megawatts (MW) of clean energy supply have completed the interconnection process” but “the NYISO estimates that just seven, representing 3,493 MW, have begun construction.” Two of the seven are the Champlain Hudson Power Express transmission line and the Alle-Catt Wind Farm.
NYISO did not mince words about the cause: “While interconnection is often cited as a reason for project delays, the number of projects with approved interconnection agreements that have not yet begun construction suggests that other factors are at play.” It cited permitting, “supply chain disruptions, access to project capital, and economic forces that drive up the costs and delivery times of equipment,” and the loss of federal tax credits.
The 2026 RNA reflects the same reality. Its base case includes only about 6,200 MW of additional planned generation because “many proposed projects that are studied in the NYISO’s processes do not enter service when planned or at all.” To be included, a project must meet “advanced interconnection, financing, procurement, or construction milestones.” Over 4,700 MW, including 2,800 MW of solar, 160 MW of land-based wind, and 1,600 MW of batteries, has completed interconnection and accepted cost allocation but has not advanced far enough to be included.
Implications for the Net-Zero Transition
I see four implications.
First, the queue numbers are not a resource plan. NYISO’s sensitivity range for planned additions by 2036 runs from 6,300 MW in the base case to 10,900 MW if every cost-allocated project is assumed to come online. One of the RNA solution combinations adds roughly 4,500 MW of projects that completed interconnection plus about 15,500 MW from the Transition Cluster Study. The RNA warns that this combination “relies on a large set of non-firm projects becoming firm, beginning construction, and entering operation.” Given that only seven of 106 projects that finished the process since 2019 had started construction by August 2025, that is a big assumption.
Second, nameplate capacity is not reliability. The RNA draft appendices estimate that 500 MW of solar provides only about 25 MW of statewide resource adequacy value in 2036, and 500 MW of land-based wind only about 75 MW, compared with about 475 MW from a New York City gas plant with firm fuel or an eight-hour New York City battery. The 14,000 MW of solar, wind, and storage in the cluster sounds impressive, but most of it is weather-dependent and contributes a fraction of its nameplate rating when the system needs it most.
Third, the costs are real and they show up in rates. The $1.93 billion in Transition Cluster upgrade allocations is paid by developers, but developers recover it in their bids for state renewable energy credits and in market prices, so ratepayers ultimately pay. These connection costs do not include the bulk transmission needed to move upstate renewables downstate.
Fourth, demand is running ahead of supply. The RNA also reports that “As of September 2026, the NYISO had 53 projects requesting to interconnect to the New York system for a combined total of over 14,000 MW of proposed large loads.” That is a third 14,000 MW figure. If load arrives on schedule and the renewables do not, the reliability needs the RNA has already identified get worse.
Discussion
NYISO deserves credit for the cluster study reforms: speculative projects dropped out early and the remaining developers have firm costs and deadlines. But the reforms expose a fact that Climate Act supporters would rather not confront. The interconnection queue was never the main reason projects were not getting built. NYISO’s own 2025 analysis points to permitting, supply chains, financing, and federal policy, and none of those are within NYISO’s control.
This matters for the Climate Act’s 2030 target in particular. The RNA’s base case is built from projects that can “reasonably be relied upon for reliability,” and that base case is short. Transition Cluster projects that settle in late 2026 still need permits, financing, equipment, and construction. There is no realistic path for these projects to close the gap to 70% renewable generation by 2030.
Large nameplate totals are easy to cite in press releases. NYISO is careful to distinguish between queue projects and projects it will count on. Policy makers should be equally careful.
The 2024 Transition Cluster Study started with about 240 projects, ended Phase 2 with 91 projects totaling about 15,500 MW, and assigned about $1.93 billion in upgrade costs. That is an improvement in process, not a guarantee of new supply. NYISO’s own record shows that only seven of 106 projects that completed interconnection since 2019 had begun construction by August 2025, and even built projects contribute a fraction of their nameplate rating to reliability.
My conclusion is the one I keep coming back to. The net-zero transition is limited by physics, permitting, supply chains, and cost, not by paperwork at NYISO. Until the Climate Act schedule is reconciled with those constraints, and with the need for firm, dispatchable resources, New York will keep reporting impressive queue numbers while its reliability margins shrink and its electric bills rise.